Project intelligenceTDLR TABS2025012995Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

FCCU - Spring Branch - Generator

9100 Westview, Houston, TX, 77079

Target date passed (Oct 2025)Review Complete

FCCU - Spring Branch - Generator is a renovation/alteration project at 9100 Westview, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Oct 2025 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $250K across about 300 sq ft.

Estimated project value
$250K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
300 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$833/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Feb 28, 2025229 days across supplied datesOct 15, 2025

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    76 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    153 days after the preceding date shown.

    Source: TDLR filing

    View source record

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77079 (Houston)

One email per change. Unsubscribe in one click. Privacy.

FCCU - Spring Branch - Generator is a Renovation/Alteration project located at 9100 Westview, Houston, TX 77079 in Houston, Texas. The project has an estimated value of $250K covering 300 sq ft. First Community Credit Union is the property owner and MG Architects is the design firm of record. The project was registered with TDLR on February 28, 2025.

Frequently Asked Questions

What is FCCU - Spring Branch - Generator?

FCCU - Spring Branch - Generator is a renovation/alteration project at 9100 Westview in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Addition of Generator and Screenwall with electrical connections

Is FCCU - Spring Branch - Generator open in Houston?

FCCU - Spring Branch - Generator was scheduled to finish construction in Oct 2025 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is FCCU - Spring Branch - Generator located?

FCCU - Spring Branch - Generator is located at 9100 Westview, Houston, TX, 77079, in Harris County.

Who is the owner or developer of FCCU - Spring Branch - Generator?

First Community Credit Union is the property owner/developer of record for FCCU - Spring Branch - Generator, per its TDLR project registration.

Who is the architect or design firm for FCCU - Spring Branch - Generator?

MG Architects is the design firm of record for FCCU - Spring Branch - Generator, according to its TDLR filing.

How much does FCCU - Spring Branch - Generator cost and how big is it?

FCCU - Spring Branch - Generator has an estimated construction value of $250K and approximately 300 square feet (about $833/sqft), based on its TDLR filing.

Scope of Work

Addition of Generator and Screenwall with electrical connections

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

9100 Westview, Houston, TX, 77079

Location by street address

Watch all construction in 77079 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.