๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

FM 487

College Ave. to SH 95 Bypass, TX, 76527
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025018063
$231K
Project Value
20,000
Square Feet
$12/sqft
Cost/SqFt
11 months
Duration
Registered:May 2, 2025
Start:Aug 1, 2026
Target:Jul 7, 2027
Remaining:558 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Rehabilitation of existing road to 4R criteria Urban Section

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 2, 2025
Review Complete
May 2, 2025
Construction Start
August 1, 2026
Expected Completion
July 7, 2027

๐Ÿ“Location & Views

Open in MapsGet Directions|30.18935, -97.31475

Quick Actions

TDLR ID: TABS2025018063

Registered Accessibility Specialist

๐Ÿ“‹
FRANK,FONSECA
RAS #1184
526 WILLIAMSBURG PL, SAN ANTONIO, TX 78201