Project intelligenceTDLR TABS2025018085New Construction
Funding type

This project is privately funded, on private land for private use.

Collective East

7000 Johnny Morris Road, Austin, TX, 78724

Target date passed (May 2026)Review Complete

Collective East is a new construction project at 7000 Johnny Morris Road, Austin, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish May 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $2.5M across about 45,778 sq ft.

Estimated project value
$2.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
45,778 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$55/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
8 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

May 2, 2025461 days across supplied datesAug 6, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    122 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    242 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    97 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Collective East

Collective East is a new construction project in the Colony Park neighborhood of Austin, comprising three single-story cold dark shell buildings with mezzanines. The site at 7000 Johnny Morris Road covers 45,778 sq ft and was registered with TDLR in May 2025. Arabon Real Estate owns the project, which is privately funded for private use.

The scope of work includes Buildings 1, 2, and 3, designed by Dick Clark + Associates. The estimated cost is $2,500,000, equating to $55 per sq ft. Construction was scheduled to begin in September 2025 and finish in May 2026, a build window of 242 days.

Project Status and Context

TDLR completed plan review in August 2026. Although the completion date on the filing has passed, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.

Compared to 6,768 new construction filings in Travis County, this project's cost is above the county median of $1,000,000. Its size of 45,778 sq ft is larger than the county median of 12,000 sq ft. The cost per square foot of $55 is below the county median of $125. The scheduled build window is close to the county median of 304 days.

Dick Clark + Associates has six other TDLR-registered projects totaling $26,700,000, including Workbench and Riverside Condominiums in Austin. City of Austin permit records show 12 permits on file at this street address, issued between September 2025 and July 2026. These include plumbing, building, and electrical permits with declared valuations totaling $2,250,000.

The project is situated in a ZIP code with a population of about 29,326 and a median household income of $76,906. Nearby businesses include Neighborhood Baptist Church and HooDoo Studio. A Facebook post described The Collective East as a hub for visionaries and entrepreneurs. The site is near other registered projects like the Colony Park Health & Wellness Center.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78724 (Austin)

One email per change. Unsubscribe in one click. Privacy.

Collective East is a New Construction project located at 7000 Johnny Morris Road, Austin, TX 78724 in Austin, Texas. The project has an estimated value of $2.5M covering 45,778 sq ft. Arabon Real Estate is the property owner and Dick Clark + Associates is the design firm of record. The project was registered with TDLR on May 2, 2025.

Frequently Asked Questions

Is Collective East open for business?

TDLR has not yet recorded a final inspection. While a Facebook post describes it as a hub for entrepreneurs, the construction record does not confirm an opening date or operational status.

Who is the developer of Collective East?

Arbon Real Estate is the owner and developer of record. The design firm is Dick Clark + Associates, and the registered accessibility specialist is David C Deming.

What is the total size of the project?

The project includes three buildings totaling 45,778 sq ft. The estimated cost is $2,500,000, which calculates to $55 per square foot.

Where is Collective East located?

It is located at 7000 Johnny Morris Road in the Colony Park neighborhood of Austin, Texas. The site is in Travis County and outside the FEMA floodplain.

When was the project registered with TDLR?

The project was registered in May 2025. Plan review was completed in August 2026, but a final inspection has not yet been recorded.

What is Collective East?

Collective East is a new construction project at 7000 Johnny Morris Road in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Work includes three single-story cold dark shell buildings with mezzanines (1,2 & 3).

Is Collective East open in Austin?

Collective East was scheduled to finish construction in May 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Who is the owner or developer of Collective East?

Arabon Real Estate is the property owner/developer of record for Collective East, per its TDLR project registration.

Who is the architect or design firm for Collective East?

Dick Clark + Associates is the design firm of record for Collective East, according to its TDLR filing.

How much does Collective East cost and how big is it?

Collective East has an estimated construction value of $2.5M and approximately 45,778 square feet (about $55/sqft), based on its TDLR filing.

Scope of Work

Work includes three single-story cold dark shell buildings with mezzanines (1,2 & 3).

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

7000 Johnny Morris Road, Austin, TX, 78724

Location by street address

Related City Permits

Building permits found at or near this location

7000 1/2 LOCHINVAR ST

AISD proposed 120 monopole tower and ground equipment. No backup batteries or generator proposed.

ActiveElectrical PermitRemodelSep 2026
View Details
2026-071345 EP
Mauldin Electric Company
7000 CONVICT HILL RD UNIT 2307

Replacement of complete existing central heat and air system with or without duct work

ActiveMechanical PermitChange OutAug 2026
View Details
2026-099207 MP
Texas Multifamily Solution, LLC
7000 BENT OAK CIR

Replacement of an existing water heater 50 Gallon Natural Gas Water Heater Replacement

FinalPlumbing PermitChange OutAug 2026
View Details
2026-096960 PP
Sweetwater Home Services
7000 CONVICT HILL RD UNIT 3206

Replacement of complete existing central heat and air system with or without duct work

FinalMechanical PermitChange OutJul 2026
View Details
2026-093127 MP
Texas Multifamily Solution, LLC
7000 JOHNNY MORRIS RD BLDG 2

Secondary Plumbing Contractor- Install 3000 of sewer pipe and 2400 of water line on the outside.

ActivePlumbing PermitPlumbing Utility ConnectionJul 2026
View Details
2026-089465 PP
Liberty Hill Plumbing

Watch all construction in 78724 (Austin)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.