New Building for Happy Fire Station

Near I-27 & FM 1075 (Southwest Corner), Happy, TX, 79042

Construction complete · May 2026Inspection Complete

New Building for Happy Fire Station is a new construction project at Near I-27 & FM 1075 (Southwest Corner), Happy, in Swisher County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed May 2026). The project has an estimated value of $750K across about 8,000 sq ft.

Estimated project value
$750K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
8,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$94/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 3, 2025354 days across supplied datesMay 23, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    13 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    189 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    152 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About New Building for Happy Fire Station

The City of Happy, Texas, completed an 8,000-square-foot new building for the Happy Fire Station at the southwest corner of I-27 and FM 1075. The project is identified in the TDLR filing as New Building for Happy Fire Station and is located in Swisher County. The structure passed its final TDLR accessibility inspection in May 2026, confirming that construction is complete.

Registered with the Texas Department of Licensing and Regulation in June 2025, the project underwent plan review and construction start in the same month. The estimated cost for the new construction and site work was $750,000, which calculates to a cost of $94 per square foot. The registered accessibility specialist for the project was Leslie Kit Carter.

The building is situated in the ZIP code 79042, where the U.S. Census Bureau’s American Community Survey five-year estimates indicate a population of about 1,181 residents. The area has a median household income of $69,219 and a median owner-occupied home value of $119,100. Housing in this region is predominantly owner-occupied, with approximately 526 housing units recorded.

Project Scope and Status

The scope of work included the construction of the new building and associated site work. The filing lists the owner as the City of Happy, Texas, and notes that the project is privately funded, on private land, and for private use. Although the initial completion date listed in the filing was December 2025, the final inspection was not passed until May 2026. The TDLR status is now marked as Inspection Complete.

Happy, Texas, is a small town in the state’s panhandle region, situated in both Randall and Swisher Counties. Third-party sources, such as a Facebook post describing the town, note its small-town character and history, mentioning that it has looked similar for decades. A Hello Little Home article also references the town’s cultural footprint, including a connection to a 1999 film. The Swisher County unemployment rate was 4.5 percent in August 2026, according to FRED data.

The completion of this 8,000-square-foot facility represents a significant infrastructure investment for the community. The project’s cost per square foot of $94 aligns with the overall budget of $750,000. With the final TDLR accessibility inspection passed in May 2026, the construction phase is officially concluded.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 79042 (Happy)

One email per change. Unsubscribe in one click. Privacy.

New Building for Happy Fire Station is a New Construction project located at Near I-27 & FM 1075 (Southwest Corner), Happy, TX 79042 in Happy, Texas. The project has an estimated value of $750K covering 8,000 sq ft. City of Happy, Texas is the property owner. The project was registered with TDLR on June 3, 2025.

Frequently Asked Questions

Is the Happy Fire Station building open?

The TDLR record confirms construction is complete, with the final inspection passed in May 2026. The provided facts do not indicate whether the business is open for public operations.

Where is the new building located?

The new building for the Happy Fire Station is located near I-27 and FM 1075 at the southwest corner in Happy, Texas 79042, within Swisher County.

What is the size and cost of the project?

The project is 8,000 square feet with an estimated cost of $750,000. This results in a cost of $94 per square foot for the new construction and site work.

Who is the owner of the project?

The owner and developer of record is the City of Happy, Texas. The project is privately funded, on private land, and for private use.

When was the project registered with TDLR?

The project was registered with the Texas Department of Licensing and Regulation in June 2025. Plan review and construction start also occurred in June 2025.

What is New Building for Happy Fire Station?

New Building for Happy Fire Station is a new construction project at Near I-27 & FM 1075 (Southwest Corner) in Happy, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New building and site work.

Is New Building for Happy Fire Station open in Happy?

Construction on New Building for Happy Fire Station is complete — TDLR records show the project passed its required accessibility inspection in May 2026. The building is finished and very likely open.

Where is New Building for Happy Fire Station located?

New Building for Happy Fire Station is located at Near I-27 & FM 1075 (Southwest Corner), Happy, TX, 79042, in Swisher County.

Who is the owner or developer of New Building for Happy Fire Station?

City of Happy, Texas is the property owner/developer of record for New Building for Happy Fire Station, per its TDLR project registration.

How much does New Building for Happy Fire Station cost and how big is it?

New Building for Happy Fire Station has an estimated construction value of $750K and approximately 8,000 square feet (about $94/sqft), based on its TDLR filing.

Scope of Work

New building and site work.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Near I-27 & FM 1075 (Southwest Corner), Happy, TX, 79042

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 79042 (Happy)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.