Trinity Forest Spine Trail - North Phase 2

Intersection of Samuell Boulevard at IH 30 WB, Dallas, TX, 75228
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2025020740
$21.5M
Project Value
145,728
Square Feet
$148/sqft
Cost/SqFt
1y 5mo
Duration
Registered:Jun 6, 2025
Start:Dec 15, 2025
Target:Apr 30, 2027
Remaining:490 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

2.3 miles of 12' wide concrete multi-use public trail including (09) nine bridges and appx. 2100 l.f. of boardwalk. The project starts at Samuell Boulevard & IH 30 and ends at the northwest corner of Lawnview Avenue at Scyene Road.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 6, 2025
Review Complete
June 6, 2025
Construction Start
December 15, 2025
Expected Completion
April 30, 2027

๐Ÿ“Location & Views

Open in MapsGet Directions|32.79289, -96.72743

Quick Actions

TDLR ID: TABS2025020740

Registered Accessibility Specialist

๐Ÿ“‹
JUSTIN K,WALTON
RAS #1329
3333 MELTON RD, SANGER, TX 76266