Project intelligenceTDLR TABS2025020833New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Sweeny Bulldog Stadium

600 Ashley Wilson rd, Sweeny, TX, 77480

Target date passed (Oct 2026)Review Complete

Sweeny Bulldog Stadium is a new construction project at 600 Ashley Wilson rd, Sweeny, in Brazoria County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Oct 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $41.0M across about 66,600 sq ft.

Estimated project value
$41.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
66,600 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$616/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 3mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 9, 2025509 days across supplied datesOct 31, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    53 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    456 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Sweeny Bulldog Stadium

Sweeny Bulldog Stadium Construction Details

The Sweeny Bulldog Stadium project involves new construction at 600 Ashley Wilson rd, Sweeny, TX 77480. Sweeny ISD is the owner of record for this significant investment in local athletic infrastructure. The filing details a 1-story press box and a 5,000 seat capacity spectator viewing grandstand surrounding an existing high school football field. Site athletic improvements are included alongside a 2 story athletic/administration building. The total scope covers 66,600 sq ft of new space.

Registered with TDLR in June 2025, the project has a planned estimated cost of $41,000,000. This results in a cost per square foot of $616. William T Winning is the registered accessibility specialist for the filing. The work is classified as new construction and involves public funds.

TDLR completed plan review in June 2025 and construction is scheduled to finish in October 2026, with work starting August 2025. The scheduled build window of 456 days is longer than the county median of 221 days. The estimated cost is above the county median for its type, which sits at $800,000 for new construction filings in Brazoria County. The size of 66,600 sq ft is also well above the median of 9,114 sq ft.

Businesses already near this site include Backyard City Park, Sweeny Community Library, Sweeny Library, Christmas Light Professionals, River Oaks Apartment Homes, and Sweeny City Hall. Sweeny ISD has one other TDLR-registered project totaling $4,600,000: Sweeny High School and Sweeny Junior High in Sweeny, which is also review complete. The project status is Review Complete.

The area profile for ZIP 77480 shows a population of about 8,252. The median household income is $63,981. There are 3,581 housing units, with a median owner-occupied home value of $189,000. Housing is predominantly owner-occupied. Brazoria County unemployment rate was 5.1 percent in August 2026, which was lower than a year earlier. The TDLR record covers construction only and does not record whether the business has started serving customers.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77480 (Sweeny)

One email per change. Unsubscribe in one click. Privacy.

Sweeny Bulldog Stadium is a New Construction project located at 600 Ashley Wilson rd, Sweeny, TX 77480 in Sweeny, Texas. The project has an estimated value of $41.0M covering 66,600 sq ft. Sweeny ISD is the property owner. The project was registered with TDLR on June 9, 2025.

Frequently Asked Questions

Who is the owner of Sweeny Bulldog Stadium?

Sweeny ISD is the owner and developer of record for the Sweeny Bulldog Stadium project located in Sweeny, Texas.

What is the total cost of the stadium construction?

The estimated cost for the new construction is $41,000,000, covering 66,600 sq ft of space including the grandstand and administration building.

When does construction start and end?

Construction is scheduled to start in August 2025 and is scheduled to finish in October 2026. Plan review was completed in June 2025.

Is the stadium open to the public?

The TDLR record covers construction only and does not record whether the business has started serving customers or is open for events.

Where is the stadium located?

The project is located at 600 Ashley Wilson rd, Sweeny, TX 77480, in Brazoria County, near Sweeny City Hall and local libraries.

What is Sweeny Bulldog Stadium?

Sweeny Bulldog Stadium is a new construction project at 600 Ashley Wilson rd in Sweeny, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: The project entails the construction of a new 1 story press box with a 5,000 seat capacity spectator viewing grandstand surrounding an existing high school football field. Site athletic improvements along with a 2 story athletic/administ…

Is Sweeny Bulldog Stadium open in Sweeny?

Sweeny Bulldog Stadium was scheduled to finish construction in Oct 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Sweeny Bulldog Stadium located?

Sweeny Bulldog Stadium is located at 600 Ashley Wilson rd, Sweeny, TX, 77480, in Brazoria County.

Who is the owner or developer of Sweeny Bulldog Stadium?

Sweeny ISD is the property owner/developer of record for Sweeny Bulldog Stadium, per its TDLR project registration.

How much does Sweeny Bulldog Stadium cost and how big is it?

Sweeny Bulldog Stadium has an estimated construction value of $41.0M and approximately 66,600 square feet (about $616/sqft), based on its TDLR filing.

Scope of Work

The project entails the construction of a new 1 story press box with a 5,000 seat capacity spectator viewing grandstand surrounding an existing high school football field. Site athletic improvements along with a 2 story athletic/administration build

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

600 Ashley Wilson rd, Sweeny, TX, 77480

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related Projects

Watch all construction in 77480 (Sweeny)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.