Funding type
This project is privately funded, on private land for private use.
MHWMC South Tower Entrance Renovation in Shenandoah, TX
9250 Pinecroft Dr, Shenandoah, TX, 77380
MHWMC South Tower Entrance Renovation is a renovation/alteration project at 9250 Pinecroft Dr, Shenandoah, in Montgomery County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2026). The project has an estimated value of $250K across about 380 sq ft.
- Estimated project value
- $250K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 380 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $658/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
5 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
18 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
39 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
377 days after the preceding date shown.
Source: TDLR filing
View source record
📰About MHWMC South Tower Entrance Renovation
The renovation of the South Tower entrance at Memorial Hermann Hospital in Shenandoah is complete. The project, filed with the Texas Department of Licensing and Regulation as the MHWMC South Tower Entrance Renovation, passed its final TDLR accessibility inspection in August 2026. This confirms that the construction work on the ground-floor entry door has concluded and the site is ready for use.
Located at 9250 Pinecroft Dr in Montgomery County, this renovation focused specifically on updating the entry door into the hospital. The scope of work included site demolition and the adjustment of related utilities as required. The total area affected by the renovation was approximately 380 square feet, a modest footprint that reflects the targeted nature of the accessibility improvements.
Project Details and Costs
Memorial Hermann Hospital System acted as the owner of record for this project. The design firm of record was PhiloWilke Partnership, which provided the plans for the renovation. William T Winning served as the registered accessibility specialist, ensuring the work met state standards. The estimated cost for the project was $250,000, which calculates to $658 per square foot.
According to the TDLR filing, the project was registered in June 2025, with plan review completed in the same month. Construction was scheduled to begin in July 2025, with a planned completion date of August 2025. However, the final inspection was not passed until August 2026, indicating that the actual construction timeline extended beyond the initial filing estimates.
Context in the Region
This renovation is part of a broader pattern of accessibility improvements in the area. Memorial Hermann Hospital System has six other TDLR-registered projects in the region, totaling $8,576,760. These include projects in Katy, Houston, Sugar Land, and Shenandoah, such as the Memorial Hermann Tower 4 renovation. The design firm, PhiloWilke Partnership, is also involved in six other projects across Texas, including work at the Shops at Spring Creek and Texas Children's Hospital in The Woodlands.
The project’s cost of $250,000 is close to the county median for renovation and alteration filings in Montgomery County. While the estimated build window of 39 days was shorter than the county median of 92 days, the actual timeline extended significantly. The per-square-foot cost of $658 is above the county median of $85, reflecting the specialized nature of hospital entrance renovations and the inclusion of utility work.
Inspection Complete
Final inspection completed, awaiting project closure
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 77380 (Shenandoah)
One email per change. Unsubscribe in one click. Privacy.
MHWMC South Tower Entrance Renovation is a Renovation/Alteration project located at 9250 Pinecroft Dr, Shenandoah, TX 77380 in Shenandoah, Texas. The project has an estimated value of $250K covering 380 sq ft. Memorial Hermann Hospital System is the property owner and PhiloWilke Partnership is the design firm of record. The project was registered with TDLR on June 19, 2025.
Frequently Asked Questions
Is the South Tower renovation complete?
Yes, the project passed its final TDLR accessibility inspection in August 2026, confirming that the construction phase is officially finished and the site is complete.
Who is the owner of the South Tower project?
The owner of record for this specific renovation project is Memorial Hermann Hospital System, which also owns several other facilities in the region.
What was the scope of the renovation work?
The work involved renovating the entry door on the ground floor, including site demolition and adjustments to related utilities as required by the filing.
How much did the project cost?
The estimated cost for the South Tower entrance renovation was $250,000, which amounts to $658 per square foot for the 380-square-foot area affected.
Who designed the renovation?
PhiloWilke Partnership was the design firm of record responsible for the plans, while William T Winning served as the registered accessibility specialist.
What is MHWMC South Tower Entrance Renovation?
MHWMC South Tower Entrance Renovation is a renovation/alteration project at 9250 Pinecroft Dr in Shenandoah, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: The project consists of the renovation of the entry door into the Memorial Hermann Hospital. The work will be done on the ground floor and is approximately 379 square feet. Work will include site demolition and include related utilities…
Is MHWMC South Tower Entrance Renovation open in Shenandoah?
Construction on MHWMC South Tower Entrance Renovation is complete — TDLR records show the project passed its required accessibility inspection in Aug 2026. The building is finished and very likely open.
Where is MHWMC South Tower Entrance Renovation located?
MHWMC South Tower Entrance Renovation is located at 9250 Pinecroft Dr, Shenandoah, TX, 77380, in Montgomery County.
Who is the owner or developer of MHWMC South Tower Entrance Renovation?
Memorial Hermann Hospital System is the property owner/developer of record for MHWMC South Tower Entrance Renovation, per its TDLR project registration.
Who is the architect or design firm for MHWMC South Tower Entrance Renovation?
PhiloWilke Partnership is the design firm of record for MHWMC South Tower Entrance Renovation, according to its TDLR filing.
How much does MHWMC South Tower Entrance Renovation cost and how big is it?
MHWMC South Tower Entrance Renovation has an estimated construction value of $250K and approximately 380 square feet (about $658/sqft), based on its TDLR filing.
Scope of Work
The project consists of the renovation of the entry door into the Memorial Hermann Hospital. The work will be done on the ground floor and is approximately 379 square feet. Work will include site demolition and include related utilities as require
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
9250 Pinecroft Dr, Shenandoah, TX, 77380
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Owner
$1.32B totalWatch all construction in 77380 (Shenandoah)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Shenandoah?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.