UTMB - East Chiller Plant Building & Utility Loop Connection
520 Texas Ave, Galveston, TX 77550, Galveston, TX, 77550
Completed100%
๐Project Metrics
TDLR #TABS2025026107$345K
Project Value
30,000
Square Feet
$12/sqft
Cost/SqFt
5 months
Duration
Registered:Aug 18, 2025
Start:Aug 1, 2025
Target:Dec 31, 2025
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New surface parking lot including ADA stalls and appropriate sidewalk / ADA access grading.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 18, 2025
Inspection Complete
+149dAugust 18, 2025
Project Closed
January 14, 2026
Construction Start
August 1, 2025
Expected Completion
December 31, 2025
๐Related Projects
Property Owner
๐ค
University of Texas Medical Branch of Galveston
Contact: Daniel Miro
View company profile
301 University Blvd, Galveston, Texas 77555
Design Firm
๐๏ธ
WALTER P MOORE
4 projects ยท $16.8M
View company profile
1301 McKinney Suite 1100, Houston, Texas 77010