Project intelligenceTDLR TABS2026002399Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) in Houston, TX

6411 FANNIN, Houston, TX, 77030

Opening ~Dec 2026Review Complete

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) is a renovation/alteration project at 6411 FANNIN, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Dec 2026. The project has an estimated value of $37.5M across about 98,810 sq ft.

Estimated project value
$37.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
98,810 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$380/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 2, 2025452 days across supplied datesDec 28, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    60 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    392 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2)

Memorial Hermann Hospital in Houston is undergoing a major renovation of its patient floors, specifically the shell and fitout for levels 10 and 11. The project, filed as MH Sarofim Pavilion Patient Shell Floors Buildout (Bp2), encompasses 98,810 square feet of space within the hospital's Medical Center Area location at 6411 Fannin. This extensive work represents a significant expansion of the facility's patient care capacity within its existing footprint.

Project Scope and Cost

The estimated cost for this renovation and alteration is $37,500,000, which translates to approximately $380 per square foot. This figure is notably above the Harris County median of $80 per square foot for similar renovation and alteration filings. The scope of work is detailed in the filing as Bid Package 2, covering the shell patient floors for levels 10 and 11, including full fitout. The project is privately funded on private land for private use by Memorial Hermann Healthcare System, the owner of record.

Timeline and Status

TDLR completed the plan review for this registered accessibility project in October 2025. Construction is scheduled to begin in December 2025 and is scheduled to finish in December 2026. This timeline represents a build window of 392 days, which is longer than the county median of 92 days for comparable projects. The TDLR status is listed as Review Complete, indicating that the regulatory approvals for the accessibility aspects of the build have been finalized.

Page Southerland Page, INC. is the design firm of record for this project. Kenneth Otten is the registered accessibility specialist associated with the filing. Memorial Hermann Healthcare System has six other TDLR-registered projects on file, with this Houston renovation being one of the largest in terms of estimated cost. The site is located in a dense medical district, near other major healthcare facilities and hotels, reflecting the area's profile as a hub for medical services in Harris County.

City of Houston permit records show two building permits issued at this address in January 2026. These permits are specifically for the 49,405 square foot buildout of Hospital Floor 10 and the 49,405 square foot buildout of Hospital Floor 11, referencing the 2021 International Building Code. These local permits align with the state-level TDLR registration and confirm the physical construction activities planned for these specific floors.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77030 (Houston)

One email per change. Unsubscribe in one click. Privacy.

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) is a Renovation/Alteration project located at 6411 FANNIN, Houston, TX 77030 in Houston, Texas. The project has an estimated value of $37.5M covering 98,810 sq ft. MEMORIAL HERMANN HEALTHCARE SYSTEM is the property owner and PAGE SOUTHERLAND PAGE, INC. is the design firm of record. The project was registered with TDLR on October 2, 2025.

Frequently Asked Questions

When is the Memorial Hermann Hospital renovation scheduled to finish?

Construction is scheduled to finish in December 2026. The project timeline indicates work starting in December 2025, with a total build window of 392 days as per the TDLR filing.

What is the estimated cost of the Memorial Hermann Hospital patient floor buildout?

The estimated cost is $37,500,000. This covers the renovation and alteration of 98,810 square feet on floors 10 and 11, resulting in a cost of approximately $380 per square foot.

Who is the design firm for the Memorial Hermann Hospital project?

Page Southerland Page, INC. is the design firm of record for this project. Kenneth Otten is listed as the registered accessibility specialist for the TDLR filing.

Is the Memorial Hermann Hospital renovation complete?

No, the project is not complete. TDLR plan review was completed in October 2025, but construction is scheduled to finish in December 2026, with work starting in December 2025.

Which floors are being renovated at Memorial Hermann Hospital?

The renovation covers the shell and fitout of patient floors 10 and 11. The filing specifically identifies this as Bid Package 2 for the shell patient floors on these levels.

What is MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2)?

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) is a renovation/alteration project at 6411 FANNIN in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: BID PACKAGE 2 - SHELL PATIENT FLOORS L10-11 FITOUT (98,810 SF)

Is MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) open in Houston?

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) is still under construction in Houston, TX, with an estimated completion of Dec 2026 according to its TDLR registration.

Where is MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) located?

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) is located at 6411 FANNIN, Houston, TX, 77030, in Harris County.

Who is the owner or developer of MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2)?

MEMORIAL HERMANN HEALTHCARE SYSTEM is the property owner/developer of record for MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2), per its TDLR project registration.

Who is the architect or design firm for MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2)?

PAGE SOUTHERLAND PAGE, INC. is the design firm of record for MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2), according to its TDLR filing.

How much does MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) cost and how big is it?

MH SAROFIM PAVILION PATIENT SHELL FLOORS BUILDOUT (BP2) has an estimated construction value of $37.5M and approximately 98,810 square feet (about $380/sqft), based on its TDLR filing.

Scope of Work

BID PACKAGE 2 - SHELL PATIENT FLOORS L10-11 FITOUT (98,810 SF)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

6411 FANNIN, Houston, TX, 77030

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Related City Permits

Building permits found at or near this location

6411 FANNIN (HERMANN PAVILION 2) ST FL 10, Houston, TX 77030

49,405 SF HOSPITAL FL 10 BUILDOUT(M/2)1-17-1-I2-A '21 IBC SPK/FA

IssuedBuilding PmtJan 2026
HOU-25096077-BUILDINGPMT
6411 FANNIN (HERMANN PAVILION 2) ST FL 11, Houston, TX 77030

49,405 SF HOSPITAL FL 11 BUILDOUT(2/2)1-17-1-I2-A '21 IBC SPK/FA

IssuedBuilding PmtJan 2026
HOU-25096078-BUILDINGPMT

Watch all construction in 77030 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.