Nelson Way Roadway Extension and Bridge Construction Project in Katy, TX

Nelson Way, Katy, Texas 77494, Katy, TX, 77494

Opening ~Nov 2026Review Complete

Nelson Way Roadway Extension and Bridge Construction Project is a new construction project at Nelson Way, Katy, Texas 77494, Katy, in Fort Bend County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Nov 2026. The project has an estimated value of $204K across about 12,400 sq ft.

Estimated project value
$204K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
12,400 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$16/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 7, 2025419 days across supplied datesNov 30, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    41 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    378 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Nelson Way Roadway Extension and Bridge Construction Project

The Nelson Way Roadway Extension and Bridge Construction Project involves the installation of a new 6-foot wide sidewalk totaling 12,400 square feet in the Katy Mills area. This new construction project, registered with TDLR in October 2025, is scheduled to finish in November 2026. The estimated cost for the work is $203,570.

Construction activity is set to begin in November 2025, following the completion of plan review in October 2025. The project involves public funds and is located on public land in Fort Bend County. The registered accessibility specialist for this filing is Kenneth Otten. The total build window spans 378 days, which is longer than the county median of 199 days for similar new construction projects.

Project Context and Location

The site is situated in ZIP code 77494, a region with a population of about 130,920 residents according to U.S. Census estimates. The median household income in this area is $144,444, and the median owner-occupied home value is $420,100. The neighborhood is predominantly owner-occupied, with 42,520 housing units recorded. Nearby businesses include the Holiday Inn & Suites Houston West - Katy Mills and Residence Inn by Marriott Houston Katy Mills, indicating a well-established commercial and lodging corridor.

The City of Katy is the owner of record for this project. The city has six other TDLR-registered projects totaling $3,828,830, including work on Katy City Park and Katy City Hall. The Nelson Way Roadway Extension and Bridge Construction Project’s cost per square foot is $16, which is below the county median of $100 for new construction filings. While the project is smaller in scale than the county median of 9,230 square feet, it fits within the bottom quarter of estimated costs for this type of work in Fort Bend County.

Fort Bend County’s unemployment rate was 5 percent in July 2026, higher than a year earlier. The construction of this sidewalk and bridge extension supports local infrastructure development. The TDLR status is Review Complete, confirming that the plans have met regulatory requirements before the start of physical work in November 2025.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77494 (Katy)

One email per change. Unsubscribe in one click. Privacy.

Nelson Way Roadway Extension and Bridge Construction Project is a New Construction project located at Nelson Way, Katy, Texas 77494, Katy, TX 77494 in Katy, Texas. The project has an estimated value of $204K covering 12,400 sq ft. City of Katy is the property owner. The project was registered with TDLR on October 7, 2025.

Frequently Asked Questions

When is the Nelson Way project scheduled to finish?

The project is scheduled to finish in November 2026. Construction is set to start in November 2025, following the completion of plan review in October 2025.

Who is the owner of the Nelson Way construction project?

The City of Katy is the owner of record. The project involves public funds and is located on public land in Fort Bend County.

How much does the Nelson Way sidewalk project cost?

The estimated cost is $203,570. This figure covers the installation of 12,400 square feet of new 6-foot wide sidewalk.

Is the Nelson Way project open to the public?

No, the project is under construction. It is scheduled to finish in November 2026, with work starting in November 2025.

What is Nelson Way Roadway Extension and Bridge Construction Project?

Nelson Way Roadway Extension and Bridge Construction Project is a new construction project at Nelson Way, Katy, Texas 77494 in Katy, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Installation of 6' wide sidewalk: 12,400 SF

Is Nelson Way Roadway Extension and Bridge Construction Project open in Katy?

Nelson Way Roadway Extension and Bridge Construction Project is still under construction in Katy, TX, with an estimated completion of Nov 2026 according to its TDLR registration.

Where is Nelson Way Roadway Extension and Bridge Construction Project located?

Nelson Way Roadway Extension and Bridge Construction Project is located at Nelson Way, Katy, Texas 77494, Katy, TX, 77494, in Fort Bend County.

Who is the owner or developer of Nelson Way Roadway Extension and Bridge Construction Project?

City of Katy is the property owner/developer of record for Nelson Way Roadway Extension and Bridge Construction Project, per its TDLR project registration.

How much does Nelson Way Roadway Extension and Bridge Construction Project cost and how big is it?

Nelson Way Roadway Extension and Bridge Construction Project has an estimated construction value of $204K and approximately 12,400 square feet (about $16/sqft), based on its TDLR filing.

Scope of Work

Installation of 6' wide sidewalk: 12,400 SF

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Nelson Way, Katy, Texas 77494, Katy, TX, 77494

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 77494 (Katy)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.