Project intelligenceTDLR TABS2026003498Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Hamilton ISD Rock Gym & Jr High Gym Renovations

400 S College St, Hamilton, TX, 76531

Target date passed (May 2026)Review Complete

Hamilton ISD Rock Gym & Jr High Gym Renovations is a renovation/alteration project at 400 S College St, Hamilton, in Hamilton County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish May 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $3.8M across about 29,289 sq ft.

Estimated project value
$3.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
29,289 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$130/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
5 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 16, 2025211 days across supplied datesMay 15, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    61 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    2 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    148 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Hamilton ISD Rock Gym & Jr High Gym Renovations

The Hamilton ISD Rock and Jr High Gym renovation project at 400 S College St in Hamilton, Texas, is a $3,800,000 alteration of existing school facilities. The scope includes the renovation of the Rock Gym, which covers 9,493 square feet, and the Jr High Gym, which covers 19,796 square feet. Together, these renovations total 29,289 square feet of work. The project is registered with TDLR under the name Hamilton ISD Rock Gym & Jr High Gym Renovations.

Hamilton ISD is the owner of record for this public project, which involves public funds. Jacob Martin, LLC serves as the design firm of record. Stephen D Macphie is the registered accessibility specialist associated with the filing. The estimated cost per square foot is $130, a figure that is above the county median of $96 for similar renovation and alteration filings in Hamilton County.

Construction Timeline and Status

TDLR completed the plan review for this project in December 2025. Construction was scheduled to begin in December 2025, with a completion date listed as May 2026. The scheduled build window was 150 days, which is close to the county median of 153 days for comparable projects. Despite the completion date having passed, TDLR has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.

This project is one of several recent filings by Hamilton ISD. The district has two other TDLR-registered projects totaling $4,700,000, including the Hamilton ISD Junior High School and the Hamilton ISD Jr High & Elementary School. Both of those projects have completed their review processes. Jacob Martin, LLC has also been the design firm for six other TDLR-registered projects across different Texas locations, with a combined value of $1,420,000.

The project is located in Hamilton, Texas, within ZIP code 76531. According to U.S. Census ACS 2023 five-year estimates for this area, the population is about 4,673, and the median household income is $55,651. The median owner-occupied home value in this ZIP code is $128,000. Hamilton County had an unemployment rate of 5 percent in July 2026, which was higher than a year earlier.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76531 (Hamilton)

One email per change. Unsubscribe in one click. Privacy.

Hamilton ISD Rock Gym & Jr High Gym Renovations is a Renovation/Alteration project located at 400 S College St in Hamilton, Texas. The project has an estimated value of $3.8M covering 29,289 sq ft. Hamilton ISD is the property owner and Jacob Martin, LLC is the design firm of record. The project was registered with TDLR on October 16, 2025.

Frequently Asked Questions

What is the total square footage of the gym renovations?

The renovation covers a total of 29,289 square feet. This includes 9,493 square feet for the Rock Gym and 19,796 square feet for the Jr High Gym.

Who is the design firm for this project?

Jacob Martin, LLC is the design firm of record for the Hamilton ISD Rock and Jr High Gym renovation project.

What is the estimated cost of the project?

The estimated cost for the renovation is $3,800,000. This works out to $130 per square foot for the 29,289 square feet of work.

When was the project registered with TDLR?

The project was registered with TDLR in October 2025. Plan review was completed in December 2025.

Is the construction finished?

TDLR has not yet recorded a final inspection. While the scheduled completion date was May 2026, the public record does not confirm the current state of the site.

What is Hamilton ISD Rock Gym & Jr High Gym Renovations?

Hamilton ISD Rock Gym & Jr High Gym Renovations is a renovation/alteration project at 400 S College St in Hamilton, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Renovation of existing Rock Gym (9,493sf) and Jr High Gym (19,796sf)

Is Hamilton ISD Rock Gym & Jr High Gym Renovations open in Hamilton?

Hamilton ISD Rock Gym & Jr High Gym Renovations was scheduled to finish construction in May 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Hamilton ISD Rock Gym & Jr High Gym Renovations located?

Hamilton ISD Rock Gym & Jr High Gym Renovations is located at 400 S College St, Hamilton, TX, 76531, in Hamilton County.

Who is the owner or developer of Hamilton ISD Rock Gym & Jr High Gym Renovations?

Hamilton ISD is the property owner/developer of record for Hamilton ISD Rock Gym & Jr High Gym Renovations, per its TDLR project registration.

Who is the architect or design firm for Hamilton ISD Rock Gym & Jr High Gym Renovations?

Jacob Martin, LLC is the design firm of record for Hamilton ISD Rock Gym & Jr High Gym Renovations, according to its TDLR filing.

How much does Hamilton ISD Rock Gym & Jr High Gym Renovations cost and how big is it?

Hamilton ISD Rock Gym & Jr High Gym Renovations has an estimated construction value of $3.8M and approximately 29,289 square feet (about $130/sqft), based on its TDLR filing.

Scope of Work

Renovation of existing Rock Gym (9,493sf) and Jr High Gym (19,796sf)

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

400 S College St, Hamilton, TX, 76531

31.70116, -98.12628

Watch all construction in 76531 (Hamilton)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Hamilton?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.