HH BT Data Center is a renovation/alteration project at 1504 Taub Loop, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Apr 2027. The project has an estimated value of $3.0M across about 3,500 sq ft.
Design review complete, construction may proceed
HH BT Data Center is a Renovation/Alteration project located at 1504 Taub Loop, Houston, TX 77030 in Houston, Texas. The project has an estimated value of $3.0M covering 3,500 sq ft. Harris County Hospital District is the property owner and AUTOARCH Architects is the design firm of record. The project was registered with TDLR on October 20, 2025.
HH BT Data Center is a renovation/alteration project at 1504 Taub Loop in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Renovation and reconfiguration of the existing Data Center and adjacent Supply Storage Rooms on the 2nd floor, along with the conversion of six rooms into additional IDR closets on three separate floors throughout the hospital.
HH BT Data Center is still under construction in Houston, TX, with an estimated completion of Apr 2027 according to its TDLR registration.
HH BT Data Center is located at 1504 Taub Loop, Houston, TX, 77030, in Harris County.
Harris County Hospital District is the property owner/developer of record for HH BT Data Center, per its TDLR project registration.
AUTOARCH Architects is the design firm of record for HH BT Data Center, according to its TDLR filing.
HH BT Data Center has an estimated construction value of $3.0M and approximately 3,500 square feet (about $849/sqft), based on its TDLR filing.
Renovation and reconfiguration of the existing Data Center and adjacent Supply Storage Rooms on the 2nd floor, along with the conversion of six rooms into additional IDR closets on three separate floors throughout the hospital.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Filed
Oct 20, 2025
Review Complete
Dec 15, 2025
Inspection Complete
Closed
56d
Review duration