๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Duncanville ISD Transportation Complex Renovations
315 Crankshaft Dr, Duncanville, TX, 75116
Construction50%
๐Project Metrics
TDLR #TABS2026004271$3.0M
Project Value
105,840
Square Feet
$29/sqft
Cost/SqFt
8 months
Duration
Registered:Oct 27, 2025
Start:Nov 3, 2025
Target:Jul 1, 2026
Remaining:187 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Repainting exterior walls and canopies, roof repairs and roof replacement, driveway resurfacing and joint sealing of parking lot, shade structure replacements, and fuel tank replacement.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 27, 2025
Review Complete
October 27, 2025
Construction Start
November 3, 2025
Expected Completion
July 1, 2026
๐Related Projects
๐คSame Owner
$3.6M totalProperty Owner
๐ค
DUNCANVILLE INDEPENDENT SCHOOL DISTRICT
Contact: Mari Zamora
4 projects ยท $3.6M
View company profile
710 S. Cedar Ridge Dr., Duncanville, Texas 75137
Design Firm
๐๏ธ
WRA Architects
4 projects ยท $53.5M
View all projects
6000 Headquarters Drive Suite #600, Plano, Texas 75024