Project intelligenceTDLR TABS2026004334Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

MHSW Hospital IR Equipment Exchange

7600 Beechnut St, Houston, TX, 77074

Construction complete · Sep 2026Inspection Complete

MHSW Hospital IR Equipment Exchange is a renovation/alteration project at 7600 Beechnut St, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $500K across about 875 sq ft.

Estimated project value
$500K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
875 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$571/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
9 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 27, 2025318 days across supplied datesSep 10, 2026

5 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    28 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    273 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    17 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About MHSW Hospital IR Equipment Exchange

Memorial Hermann Southwest Hospital completed an interior renovation of its radiology department in September 2026. The project involved remodeling approximately 875 square feet of existing space on the first floor to facilitate an interventional radiology equipment exchange. The building passed its final TDLR accessibility inspection, confirming that construction is complete and the work has concluded.

The renovation was registered with the Texas Department of Licensing and Regulation under the project name MHSW Hospital IR Equipment Exchange. The filing specified that the scope was limited to interior remodeling only, ensuring the new equipment fit within the existing hospital infrastructure. The estimated cost for this specific work was $500,000, translating to a cost of $571 per square foot.

Project Details and Context

Memorial Hermann served as the owner of record for this project, which took place at 7600 Beechnut Street in the Sharpstown area of Houston. BSA-Architects was the design firm of record, overseeing the plan review process that was completed in October 2025. Construction was scheduled to begin in November 2025, with a planned completion date of August 2026. The final inspection was passed in September 2026, marking the end of the construction phase.

Compared to other renovation and alteration filings in Harris County, this project’s estimated cost is above the county median of $250,000. The scheduled build window of 273 days was longer than the county median of 92 days. Similarly, the cost per square foot of $571 is above the county median of $80 per square foot. These figures reflect the specialized nature of hospital radiology upgrades, which often require precise coordination and higher material costs than standard commercial renovations.

Memorial Hermann has six other TDLR-registered projects totaling $3,580,000, including facilities in Sugar Land, Houston, and Katy. BSA-Architects has been involved in six other registered projects totaling $6,790,000, indicating a consistent partnership on regional healthcare and commercial developments. The project is privately funded on private land for private use, with no public funding sources listed in the registration records.

City of Houston permit records show one permit on file at this street address, issued in March 2026. The permit type is Building Pmt, described as an 875 SF Hospital Remodel. This aligns with the scope and size detailed in the TDLR filing, providing additional verification of the construction activity at the site.

Inspection Complete

Final inspection completed, awaiting project closure

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77074 (Houston)

One email per change. Unsubscribe in one click. Privacy.

MHSW Hospital IR Equipment Exchange is a Renovation/Alteration project located at 7600 Beechnut St, Houston, TX 77074 in Houston, Texas. The project has an estimated value of $500K covering 875 sq ft. Memorial Hermann is the property owner and BSA-Architects is the design firm of record. The project was registered with TDLR on October 27, 2025.

Frequently Asked Questions

Is the renovation at Memorial Hermann Southwest Hospital complete?

Yes, the building passed its final TDLR accessibility inspection in September 2026. This confirms that the construction phase for the IR Equipment Exchange project is finished.

What was the scope of the work at 7600 Beechnut St?

The project involved interior remodeling of approximately 875 square feet of the existing Hospital Radiology Department on the first floor. The work was specifically for an IR Equipment Exchange.

Who designed the project?

BSA-Architects was the design firm of record for this renovation. They handled the plan review, which was completed in October 2025.

How much did the renovation cost?

The estimated cost for the project was $500,000. This amounts to $571 per square foot for the 875 square feet of space renovated.

When did construction start and finish?

Construction started in November 2025. The project was scheduled for completion in August 2026, and the final inspection was passed in September 2026.

What is MHSW Hospital IR Equipment Exchange?

MHSW Hospital IR Equipment Exchange is a renovation/alteration project at 7600 Beechnut St in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Interior remodeling of approximately 875 S.F. of an existing Hospital Radiology Department on the First floor for an IR Equipment Exchange. Interior Remodeling Only.

Is MHSW Hospital IR Equipment Exchange open in Houston?

Construction on MHSW Hospital IR Equipment Exchange is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is MHSW Hospital IR Equipment Exchange located?

MHSW Hospital IR Equipment Exchange is located at 7600 Beechnut St, Houston, TX, 77074, in Harris County.

Who is the owner or developer of MHSW Hospital IR Equipment Exchange?

Memorial Hermann is the property owner/developer of record for MHSW Hospital IR Equipment Exchange, per its TDLR project registration.

Who is the architect or design firm for MHSW Hospital IR Equipment Exchange?

BSA-Architects is the design firm of record for MHSW Hospital IR Equipment Exchange, according to its TDLR filing.

How much does MHSW Hospital IR Equipment Exchange cost and how big is it?

MHSW Hospital IR Equipment Exchange has an estimated construction value of $500K and approximately 875 square feet (about $571/sqft), based on its TDLR filing.

Scope of Work

Interior remodeling of approximately 875 S.F. of an existing Hospital Radiology Department on the First floor for an IR Equipment Exchange. Interior Remodeling Only.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

7600 Beechnut St, Houston, TX, 77074

Location by street address

Related City Permits

Building permits found at or near this location

7600 BEECHNUT ST, Houston, TX 77074

875 SF HOSPITAL REMODEL 1-12-1-I2-A SPK '21 IBC

IssuedBuilding PmtMar 2026
HOU-25102275-BUILDINGPMT

Watch all construction in 77074 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.