Tamarron Pond 13 Landscape Improvements
Tamarron Crossing and Raymond Franz Parkway, Fulshear, TX, 77423
Construction50%
๐Project Metrics
TDLR #TABS2026006621$678K
Project Value
327,000
Square Feet
$2/sqft
Cost/SqFt
2 months
Duration
Registered:Nov 24, 2025
Start:Jan 1, 2026
Target:Mar 1, 2026
Remaining:65 days
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Sidewalks, landscaping, irrigation, hydromulch
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
+26dNovember 24, 2025
Review Complete
December 20, 2025
Construction Start
January 1, 2026
Expected Completion
March 1, 2026
๐Related Projects
๐Nearby Projects
Within 1 kmProperty Owner
๐ค
D R HORTON
Contact: Austin Brauel
4 projects ยท $2.4M
View company profile
6744 Horton Vista Drive Ste. 100, Richmond, Texas 77407