๐Project Registered๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Camino Real Approach Roadway Realignment
100 South Monroe Street, Eagle Pass, TX, 78852
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026006714$23.0M
Project Value
705,000
Square Feet
$33/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Nov 25, 2025
Start:Mar 6, 2026
Target:Sep 8, 2027
Remaining:621 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Construction of the realignment of approach roadways to port of entry consisting of grading, asphalt concrete pavement, concrete pavement, bridge structures, storm sewer, signing and pavement markings.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 25, 2025
Construction Start
March 6, 2026
Expected Completion
September 8, 2027
๐Related Projects
Property Owner
๐ค
CITY OF EAGLE PASS
Contact: Eduardo Soto
4 projects ยท $35.0M
View company profile
100 South Monroe Street, Eagle Pass, Texas 78852
Design Firm
๐๏ธ
RRP CONSULTING ENGINEERS
View company profile
5805 Callaghan Road Suite 202, San Antonio, Texas 78228