FIFA World Cup 2026 is a renovation/alteration project at 900 E. Randol Mill road, Arlington, in Tarrant County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jun 2026). The project has an estimated value of $2.5M across about 50,000 sq ft.
- Estimated project value
- $2.5M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 50,000 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $50/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 5 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
5 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
96 days after the preceding date shown.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
27 days after the preceding date shown.
Source: TDLR filing
View source recordInspection complete · TDLR filing
The filing records completion of the accessibility inspection.
69 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
41 days after the preceding date shown.
Source: TDLR filing
View source record
📰About FIFA World Cup 2026
AT&T Stadium in Arlington completed its final TDLR accessibility inspection in June 2026, marking the end of a $2,500,000 renovation project. The work, filed under the name FIFA World Cup 2026, involved temporary installations to support international matches at the 900 E. Randol Mill Road facility. This specific filing covers 50,000 square feet of alterations, resulting in a calculated cost of $50 per square foot.
The scope of work was defined by the need to install temporary commodities for FIFA, including membrane structures, trailers, modular buildings, and temporary power systems. The project also required expanding the stadium perimeter with fencing. These changes were designed to accommodate the specific infrastructure needs of the 2026 World Cup matches held at the venue.
Project Scope and Financials
The estimated cost of $2,500,000 places this project above the median estimated cost of $250,000 for renovation and alteration filings in Tarrant County. While the total expenditure is in the top quarter for this type of work, the cost per square foot of $50 is below the county median of $79. The scheduled build window for this project was 137 days, which is longer than the county median of 92 days for similar renovations.
Trey Yelverton is listed as the owner or developer of record for this privately funded project on private land. Vlmk served as the design firm, a company that also registered another project at NRG Park in Houston with an estimated cost of $2,000,000. Ross A Thomas was the registered accessibility specialist associated with the filing, which was registered with TDLR in December 2025.
Plan review for the project was completed in April 2026, and construction began in March 2026. The final inspection passed in June 2026, and the TDLR status is recorded as Inspection Complete. This confirms that the physical work described in the filing, including the temporary structures and fencing, has been finished and verified for accessibility compliance.
Inspection Complete
Final inspection completed, awaiting project closure
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 76011 (Arlington)
One email per change. Unsubscribe in one click. Privacy.
FIFA World Cup 2026 is a Renovation/Alteration project located at 900 E. Randol Mill road, Arlington, TX 76011 in Arlington, Texas. The project has an estimated value of $2.5M covering 50,000 sq ft. Trey Yelverton is the property owner and VLMK is the design firm of record. The project was registered with TDLR on December 10, 2025.
Frequently Asked Questions
Is AT&T Stadium open for business?
The TDLR record confirms the construction and accessibility inspection are complete, but it does not provide information regarding general business hours or public opening status.
What specific work was done at AT&T Stadium?
The project involved installing temporary membrane structures, trailers, modular buildings, and temporary power, along with expanding the perimeter fencing to support FIFA World Cup 2026 matches.
Who is the design firm for this project?
Vlmk is the design firm of record. They also registered a separate $2,000,000 project at NRG Park in Houston.
When was the final inspection completed?
The final TDLR accessibility inspection was passed in June 2026, with the project status recorded as Inspection Complete.
What is the estimated cost of the renovation?
The estimated cost for this 50,000 square foot project is $2,500,000, which equates to $50 per square foot.
What is FIFA World Cup 2026?
FIFA World Cup 2026 is a renovation/alteration project at 900 E. Randol Mill road in Arlington, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: In support of the FIFA World Cup matches being held at AT&T Stadium, FIFA intends to install TEMPORARY commodities (membrane structures, trailers, modular buildings, temp power) expanding the perimeter with fencing.
Is FIFA World Cup 2026 open in Arlington?
Construction on FIFA World Cup 2026 is complete — TDLR records show the project passed its required accessibility inspection in Jun 2026. The building is finished and very likely open.
Where is FIFA World Cup 2026 located?
FIFA World Cup 2026 is located at 900 E. Randol Mill road, Arlington, TX, 76011, in Tarrant County.
Who is the owner or developer of FIFA World Cup 2026?
Trey Yelverton is the property owner/developer of record for FIFA World Cup 2026, per its TDLR project registration.
Who is the architect or design firm for FIFA World Cup 2026?
VLMK is the design firm of record for FIFA World Cup 2026, according to its TDLR filing.
How much does FIFA World Cup 2026 cost and how big is it?
FIFA World Cup 2026 has an estimated construction value of $2.5M and approximately 50,000 square feet (about $50/sqft), based on its TDLR filing.
Scope of Work
In support of the FIFA World Cup matches being held at AT&T Stadium, FIFA intends to install TEMPORARY commodities (membrane structures, trailers, modular buildings, temp power) expanding the perimeter with fencing.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
900 E. Randol Mill road, Arlington, TX, 76011
Explore the supplied address
A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.
Related Projects
Same Design Firm
$2.5M totalWatch all construction in 76011 (Arlington)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Arlington?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.