๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

42855 7-11 McLendon TX @ FM 550 & SH 205

FM 550 & SH 205, McLendon-Chisholm, TX 75132, Chisholm, TX, 75132
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026009557
$950K
Project Value
4,746
Square Feet
$200/sqft
Cost/SqFt
10 months
Duration
Registered:Jan 8, 2026
Start:May 8, 2026
Target:Feb 26, 2027
Remaining:363 days
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

New construction of a convenience store with fuel sales.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
+35d
January 8, 2026
Review Complete
February 12, 2026
Construction Start
May 8, 2026
Expected Completion
February 26, 2027