Project intelligenceTDLR TABS2026010388New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Lakeshore Park Improvements in Cleburne, TX

3370 S Nolan River Road, Cleburne, TX, 76033

Opening ~Oct 2027Review Complete

Lakeshore Park Improvements is a new construction project at 3370 S Nolan River Road, Cleburne, in Johnson County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Oct 2027. The project has an estimated value of $12.0M across about 4,160 sq ft.

Estimated project value
$12.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
4,160 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$2.88K/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jan 19, 2026650 days across supplied datesOct 31, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    18 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    83 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    549 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Lakeshore Park Improvements

The City of Cleburne is undertaking a $12,000,000 new construction project known as Lakeshore Park Improvements, located at 3370 S Nolan River Road in Johnson County. This comprehensive redevelopment involves the demolition of existing site features and the construction of significant park improvements. The project is registered with TDLR and is scheduled to finish in October 2027, with construction work set to begin in April 2026.

The scope of work for Lakeshore Park Improvements includes the installation of new sidewalks, a playground, a boat ramp, and fishing piers. Additionally, the project will feature new restroom facilities totaling 1,260 square feet and picnic pavilions spanning 2,900 square feet. The total square footage for the new construction is 4,160 sq ft. This scale of improvement represents a substantial investment in public infrastructure for the Cleburne area.

Project Context and Comparison

Kimley-Horn serves as the design firm of record for Lakeshore Park Improvements. The estimated cost of $12,000,000 places this project in the top quarter of new construction filings in Johnson County, where the median estimated cost is $760,000. The scheduled build window of 549 days is longer than the county median of 222 days. The cost per square foot is $2885, which is above the county median of $133 per sq ft. This project is one of several registered by the City of Cleburne, which has six other TDLR-registered projects totaling $5,004,600.

TDLR completed plan review in February 2026. The project status is Review Complete. Local coverage on cleburne.net has described the project as involving infrastructure improvements, with an anticipated construction start in July 2026, though the TDLR filing lists April 2026. Scout Grants reported on City of Cleburne Bid 26-01 for this project, noting that the opportunity is no longer accepting applications.

The City of Cleburne is the owner of record. George A Patterson is the registered accessibility specialist. The project involves public funds and public land. The area surrounding the project has a population of about 28,246, with a median household income of $69,870 according to U.S. Census estimates for ZIP 76033. The median owner-occupied home value in this area is $230,600.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76033 (Cleburne)

One email per change. Unsubscribe in one click. Privacy.

Lakeshore Park Improvements is a New Construction project located at 3370 S Nolan River Road,, Cleburne, TX 76033 in Cleburne, Texas. The project has an estimated value of $12.0M covering 4,160 sq ft. City of Cleburne is the property owner and Kimley-Horn is the design firm of record. The project was registered with TDLR on January 19, 2026.

Frequently Asked Questions

When is the Lakeshore Park Improvements project scheduled to finish?

Construction is scheduled to finish in October 2027. The project timeline indicates work will start in April 2026, with TDLR plan review completed in February 2026.

What is the total cost of the Lakeshore Park Improvements?

The estimated cost for the Lakeshore Park Improvements project is $12,000,000. This figure includes demolition of existing features and the construction of new park amenities such as sidewalks, playgrounds, and pavilions.

Who is the design firm for this project?

Kimley-Horn is the design firm of record for the Lakeshore Park Improvements project. The City of Cleburne is the owner/developer of record for this new construction effort.

Is the Lakeshore Park Improvements project open to the public?

The project is under construction and not yet open to the public. It is a new construction project with a scheduled completion date in October 2027. Third-party sources have described it as an ongoing refresh of the park.

What is the square footage of the new facilities?

The new construction totals 4,160 sq ft. This includes 1,260 SF for restroom facilities and 2,900 SF for picnic pavilions, along with other site features like sidewalks and a boat ramp.

What is Lakeshore Park Improvements?

Lakeshore Park Improvements is a new construction project at 3370 S Nolan River Road in Cleburne, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Demolition of existing site features, and construction of park improvements including sidewalks, playground, boat ramp, fishing piers, restroom facilities (1,260 SF), and picnic pavilions (2,900 SF).

Is Lakeshore Park Improvements open in Cleburne?

Lakeshore Park Improvements is still under construction in Cleburne, TX, with an estimated completion of Oct 2027 according to its TDLR registration.

Where is Lakeshore Park Improvements located?

Lakeshore Park Improvements is located at 3370 S Nolan River Road, Cleburne, TX, 76033, in Johnson County.

Who is the owner or developer of Lakeshore Park Improvements?

City of Cleburne is the property owner/developer of record for Lakeshore Park Improvements, per its TDLR project registration.

Who is the architect or design firm for Lakeshore Park Improvements?

Kimley-Horn is the design firm of record for Lakeshore Park Improvements, according to its TDLR filing.

How much does Lakeshore Park Improvements cost and how big is it?

Lakeshore Park Improvements has an estimated construction value of $12.0M and approximately 4,160 square feet (about $2.88K/sqft), based on its TDLR filing.

Scope of Work

Demolition of existing site features, and construction of park improvements including sidewalks, playground, boat ramp, fishing piers, restroom facilities (1,260 SF), and picnic pavilions (2,900 SF).

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

3370 S Nolan River Road, Cleburne, TX, 76033

Loading location map…
32.27751, -97.41298

Watch all construction in 76033 (Cleburne)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Cleburne?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.