Project intelligenceTDLR TABS2026010786Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Edgewood ISD - CTE

804 E. Pine St., Edgewood, TX, 75117

Target date passed (Apr 2026)Review Complete

Edgewood ISD - CTE is a additions to existing building project at 804 E. Pine St., Edgewood, in Van Zandt County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Apr 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $4.0M across about 22,300 sq ft.

Estimated project value
$4.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
22,300 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$179/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1 year
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 30, 2025365 days across supplied datesApr 30, 2026

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    268 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    4 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    93 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Edgewood ISD - CTE

Edgewood ISD is adding a 22,300 square foot Career and Technical Education (CTE) facility to its existing campus at 804 E. Pine St. in Edgewood, Texas. This $4,000,000 project, filed with the Texas Department of Licensing and Regulation (TDLR) under the name Edgewood ISD - CTE, represents a significant expansion of the district’s vocational training capabilities in Van Zandt County.

The construction scope involves a new addition to the existing building, with work scheduled to begin in April 2025 and completion targeted for April 2026. Although the scheduled completion date has passed, TDLR has not yet recorded a final inspection, meaning the official status of the site remains unconfirmed in the public record. Plan review for the project was completed in January 2026, and the project was registered with TDLR in the same month.

Project Context and Comparisons

This addition is notably larger and more expensive than the median construction project in the area. Among 19 similar additions to existing buildings registered in Van Zandt County, the median estimated cost is $600,000 and the median size is 8,126 square feet. The Edgewood CTE project’s cost sits in the top quarter of these filings, while its scheduled build window of 365 days is longer than the county median of 184 days. However, the cost per square foot for this project is $179, which is below the county median of $232 per square foot.

Edgewood ISD is the owner of record, with GLS serving as the design firm. GLS has worked on six other TDLR-registered projects totaling over $36 million, including the Fain Theater in Livingston and the Wills Point Jr. High & High School CTE facility. The Edgewood district also has three other registered projects, including a $20 million Elementary/Middle School Phase 2 project.

Local third-party sources have provided updates on the project’s progress. A Facebook post by glstex described the facility as a completed project, stating that the new 22,300 square foot building provides Edgewood High School with much-needed space for Career and Technical Education. Similarly, an Instagram post noted the completion of the CTE building, highlighting its role in building skills and confidence for students. These posts align with the project’s scope but do not replace the official TDLR inspection status.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75117 (Edgewood)

One email per change. Unsubscribe in one click. Privacy.

Edgewood ISD - CTE is a Additions to Existing Building project located at 804 E. Pine St., Edgewood, TX 75117 in Edgewood, Texas. The project has an estimated value of $4.0M covering 22,300 sq ft. Edgewood ISD is the property owner and GLS is the design firm of record. The project was registered with TDLR on January 23, 2026.

Frequently Asked Questions

Is the CTE building in Edgewood open?

TDLR has not yet recorded a final inspection, so the official status is unconfirmed. However, a Facebook post by glstex described the project as a completed facility for Edgewood High School.

Who is building the CTE addition in Edgewood?

Edgewood ISD is the owner of record, and GLS is the design firm listed in the TDLR filing for the 22,300 square foot addition.

How much does the Edgewood CTE project cost?

The estimated cost for the new 22,300 square foot addition is $4,000,000, which places it in the top quarter of similar projects in Van Zandt County.

When was the Edgewood CTE project registered with TDLR?

The project was registered with TDLR in January 2026, and plan review was also completed in January 2026.

What is Edgewood ISD - CTE?

Edgewood ISD - CTE is a additions to existing building project at 804 E. Pine St. in Edgewood, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New 22,300 SF CTE addition

Is Edgewood ISD - CTE open in Edgewood?

Edgewood ISD - CTE was scheduled to finish construction in Apr 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Edgewood ISD - CTE located?

Edgewood ISD - CTE is located at 804 E. Pine St., Edgewood, TX, 75117, in Van Zandt County.

Who is the owner or developer of Edgewood ISD - CTE?

Edgewood ISD is the property owner/developer of record for Edgewood ISD - CTE, per its TDLR project registration.

Who is the architect or design firm for Edgewood ISD - CTE?

GLS is the design firm of record for Edgewood ISD - CTE, according to its TDLR filing.

How much does Edgewood ISD - CTE cost and how big is it?

Edgewood ISD - CTE has an estimated construction value of $4.0M and approximately 22,300 square feet (about $179/sqft), based on its TDLR filing.

Scope of Work

New 22,300 SF CTE addition

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

804 E. Pine St., Edgewood, TX, 75117

Loading location map…
32.69386, -95.87531

Watch all construction in 75117 (Edgewood)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Edgewood?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.