๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

TPG 299- EV CHARGER STATIONS

6750-A FM 1463, Fulshear, TX 77441, Fulshear, TX, 77441
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2026010879
$750K
Project Value
2,200
Square Feet
$341/sqft
Cost/SqFt
2 months
Duration
Registered:Jan 26, 2026
Start:Dec 12, 2025
Target:Jan 30, 2026
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

CONSTRUCTION OF EV CHARGING STATIONS AND EQUIPMENT ON AN EXISTING SHELL STATION

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
+11d
January 26, 2026
Review Complete
February 6, 2026
Construction Start
December 12, 2025
Expected Completion
January 30, 2026

๐Ÿ“Location & Views

Open in MapsGet Directions|29.71438, -95.84628

Get alerts for Fort Bend

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists