Project intelligenceTDLR TABS2026017991New Construction
Funding type

This project is privately funded, on private land for private use.

Lakesong Blvd. in Midlothian, TX

4100 Kimble Road, Midlothian, TX, 76065

Target date passed (Oct 2026)Review Complete

Lakesong Blvd. is a new construction project at 4100 Kimble Road, Midlothian, in Ellis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Oct 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $50K across about 10,000 sq ft.

Estimated project value
$50K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
10,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$5/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
1y 7mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 1, 2025579 days across supplied datesOct 1, 2026

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    412 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    34 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    133 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Lakesong Blvd.

Lakesong Blvd. in Midlothian is a new construction project focused entirely on site accessibility improvements. The work covers 10,000 square feet of exterior enhancements, including sidewalks, accessible routes, curb ramps, pedestrian ramps, landings, and detectable warnings. This project is privately funded on private land for private use, with an estimated cost of $50,000.

The owner of record is HC GPM LLC, and the design firm of record is Graham Associates Incorporated. Bonita L Anderson serves as the registered accessibility specialist for this filing. The project is located at 4100 Kimble Road in Ellis County. TDLR completed plan review in May 2026, and the work is scheduled to finish in October 2026, with construction starting in March 2025.

Scope and Scale

The scope of work is strictly defined by the filing as site accessibility improvements necessary to comply with TAS and ADA standards. This includes the installation of curb ramps, pedestrian ramps, landings, and detectable warnings, along with related exterior improvements. The total square footage is 10,000 sq ft, resulting in a computed cost of $5 per sq ft. This figure is below the county median of $148 per sq ft for similar new construction filings in Ellis County.

HC GPM LLC has five other TDLR-registered projects in Midlothian, all with an estimated cost of $50,000. Graham Associates Incorporated is also the design firm for these five other projects. The scheduled build window for Lakesong Blvd. is 579 days, which is longer than the county median of 244 days for new construction projects in the region.

Local Context

Midlothian is located in Ellis County, where the unemployment rate was 4.5 percent in July 2026. The ZIP code 76065 has a population of about 44,614 and a median household income of $123,664, according to U.S. Census ACS 2023 five-year estimates. Housing in this area is predominantly owner-occupied, with a median home value of $378,600. This project adds to the existing infrastructure in a community with 15,081 housing units.

The TDLR status for this project is Review Complete. Construction began in March 2025, and the project is scheduled to finish in October 2026. The filing does not indicate any changes to the original scope or cost estimates. All facts presented here are derived from the official TDLR registration and related public data.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 76065 (Midlothian)

One email per change. Unsubscribe in one click. Privacy.

Lakesong Blvd. is a New Construction project located at 4100 Kimble Road, Midlothian, TX 76065 in Midlothian, Texas. The project has an estimated value of $50K covering 10,000 sq ft. HC GPM LLC is the property owner and Graham Associates Incorporated is the design firm of record. The project was registered with TDLR on April 17, 2026.

Frequently Asked Questions

What is the estimated cost for the Lakesong Blvd. project?

The estimated cost for this new construction project is $50,000. This amount covers site accessibility improvements including sidewalks, curb ramps, and detectable warnings on private land in Midlothian.

Who is the owner and design firm for this project?

HC GPM LLC is the owner of record, and Graham Associates Incorporated is the design firm of record. Bonita L Anderson is the registered accessibility specialist for the filing.

When is the construction scheduled to finish?

Construction started in March 2025 and is scheduled to finish in October 2026. TDLR completed the plan review process in May 2026, confirming the final timeline for the accessibility improvements.

What specific accessibility features are included in the scope?

The scope includes sidewalks, accessible routes, curb ramps, pedestrian ramps, landings, and detectable warnings. These exterior improvements are necessary to comply with TAS and ADA standards for the 10,000 sq ft site.

Is this project publicly funded?

No, this project is privately funded. It is located on private land for private use, and the filing indicates no public funding sources are involved in the construction of the accessibility improvements.

What is Lakesong Blvd.?

Lakesong Blvd. is a new construction project at 4100 Kimble Road in Midlothian, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Site accessibility improvements including sidewalks, accessible routes, curb ramps, pedestrian ramps, landings, detectable warnings, and related exterior improvements necessary to comply with TAS and ADA.

Is Lakesong Blvd. open in Midlothian?

Lakesong Blvd. was scheduled to finish construction in Oct 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is Lakesong Blvd. located?

Lakesong Blvd. is located at 4100 Kimble Road, Midlothian, TX, 76065, in Ellis County.

Who is the owner or developer of Lakesong Blvd.?

HC GPM LLC is the property owner/developer of record for Lakesong Blvd., per its TDLR project registration.

Who is the architect or design firm for Lakesong Blvd.?

Graham Associates Incorporated is the design firm of record for Lakesong Blvd., according to its TDLR filing.

How much does Lakesong Blvd. cost and how big is it?

Lakesong Blvd. has an estimated construction value of $50K and approximately 10,000 square feet (about $5/sqft), based on its TDLR filing.

Scope of Work

Site accessibility improvements including sidewalks, accessible routes, curb ramps, pedestrian ramps, landings, detectable warnings, and related exterior improvements necessary to comply with TAS and ADA.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

4100 Kimble Road, Midlothian, TX, 76065

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 76065 (Midlothian)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Midlothian?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.