Project intelligenceTDLR TABS2026023287Renovation/Alteration
Funding type

This project is privately funded, on private land for private use.

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out in Frisco, TX

7600 Better Way, Frisco, TX, 75033

Target date passed (Oct 2026)Review Complete

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out is a renovation/alteration project at 7600 Better Way, Frisco, in Collin County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Oct 2026 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $1.5M across about 2,000 sq ft.

Estimated project value
$1.5M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
2,000 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$773/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
4 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 18, 2026127 days across supplied datesOct 23, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    11 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    2 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    114 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About BSW The Heart Hospital Firsco - CVOR 4 Finish-Out

Baylor Scott & White The Heart Hospital - Frisco is undergoing a focused renovation at 7600 Better Way, Frisco, TX 75033. The project, filed as BSW The Heart Hospital Firsco - CVOR 4 Finish-Out, involves finishing out 2,000 sq ft of existing shell space. The work converts the area into a new Cardiac Vascular Operating Room (CVOR 4), adds a new sub-sterile zone, and extends the existing sterile core. Construction started in June 2026 and is scheduled to finish in October 2026.

The estimated cost for this renovation/alteration project is $1,545,000. This places the project in the top quarter of estimated costs for similar filings in Collin County, where the median is $220,000. The cost per square foot is $772, which is above the county median of $78 per square foot for renovation and alteration work. The scheduled build window of 116 days is longer than the county median of 92 days.

Project Details and Stakeholders

Baylor Scott & White is the owner of record for this facility in Collin County. The design firm of record is E4H Architecture. The registered accessibility specialist for the project is Bonita L Anderson. The project is privately funded on private land for private use. TDLR completed plan review in July 2026, and the status is listed as Review Complete.

Baylor Scott & White has six other TDLR-registered projects totaling $63,250,000. These include facilities in Grapevine, Arlington, Temple, and College Station. E4H Architecture has six other TDLR-registered projects totaling $4,367,000, including work in Laredo, Denton, and McKinney.

The project is situated in ZIP code 75033. U.S. Census ACS 2023 five-year estimates for this area indicate a population of about 50,292 and a median household income of $171,640. The area has 16,717 housing units, with a median owner-occupied home value of $606,500. Housing in this ZIP code is predominantly owner-occupied. Collin County’s unemployment rate was 4.6 percent in July 2026, higher than a year earlier.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75033 (Frisco)

One email per change. Unsubscribe in one click. Privacy.

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out is a Renovation/Alteration project located at 7600 Better Way, Frisco, TX 75033 in Frisco, Texas. The project has an estimated value of $1.5M covering 2,000 sq ft. Baylor Scott & White is the property owner and E4H Architecture is the design firm of record. The project was registered with TDLR on June 18, 2026.

Frequently Asked Questions

What is the scope of work for this project?

The scope includes finishing out 2,000 sq ft of existing shell space into CVOR 4, creating a new sub-sterile area, and extending the existing sterile core.

Who is the design firm?

E4H Architecture is the design firm of record for the Baylor Scott & White The Heart Hospital - Frisco renovation.

When is the project scheduled to finish?

Construction started in June 2026 and is scheduled to finish in October 2026.

Is the hospital open?

The TDLR record tracks construction status, not business operations. The project is scheduled to finish in October 2026, but operational status is not specified in the filing.

What is BSW The Heart Hospital Firsco - CVOR 4 Finish-Out?

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out is a renovation/alteration project at 7600 Better Way in Frisco, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: 2000 SF finishing-out an existing shell space into the CVOR 4, new sub sterile, and extending the existing sterile core.

Is BSW The Heart Hospital Firsco - CVOR 4 Finish-Out open in Frisco?

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out was scheduled to finish construction in Oct 2026 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.

Where is BSW The Heart Hospital Firsco - CVOR 4 Finish-Out located?

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out is located at 7600 Better Way, Frisco, TX, 75033, in Collin County.

Who is the owner or developer of BSW The Heart Hospital Firsco - CVOR 4 Finish-Out?

Baylor Scott & White is the property owner/developer of record for BSW The Heart Hospital Firsco - CVOR 4 Finish-Out, per its TDLR project registration.

Who is the architect or design firm for BSW The Heart Hospital Firsco - CVOR 4 Finish-Out?

E4H Architecture is the design firm of record for BSW The Heart Hospital Firsco - CVOR 4 Finish-Out, according to its TDLR filing.

How much does BSW The Heart Hospital Firsco - CVOR 4 Finish-Out cost and how big is it?

BSW The Heart Hospital Firsco - CVOR 4 Finish-Out has an estimated construction value of $1.5M and approximately 2,000 square feet (about $773/sqft), based on its TDLR filing.

Scope of Work

2000 SF finishing-out an existing shell space into the CVOR 4, new sub sterile, and extending the existing sterile core.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

7600 Better Way, Frisco, TX, 75033

Loading location map…
33.21034, -96.81608

Watch all construction in 75033 (Frisco)