Project intelligenceTDLR TABS2026023517Additions to Existing Building
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Joaquin ISD CTE

10901 US Hwy 84 E., Joaquin, TX, 75954

Opening ~Jun 2027Review Complete

Joaquin ISD CTE is a additions to existing building project at 10901 US Hwy 84 E., Joaquin, in Shelby County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jun 2027. The project has an estimated value of $975K across about 5,485 sq ft.

Estimated project value
$975K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,485 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$178/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
10 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

Explore the linked construction record and source history

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 22, 2026344 days across supplied datesJun 1, 2027

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    13 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    40 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    291 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Joaquin ISD CTE

Joaquin High School is the site of a $975,000 addition and renovation project filed as Joaquin ISD CTE. The work, registered with the Texas Department of Licensing and Regulation (TDLR) in June 2026, involves adding a lobby and renovating interior classrooms at the existing facility in Joaquin, Texas. The project is scheduled to finish in June 2027, with construction beginning in August 2026.

Project Scope and Design

The scope of work includes the addition of a lobby to the existing CTE building and a full renovation of the interior classrooms. This is classified as an addition to an existing building. GLS serves as the design firm of record. Phillip Bertram Chapman is the registered accessibility specialist listed on the filing. The project involves public funds and public land. The estimated cost is $975,000 for 5,485 square feet, resulting in a cost of $178 per square foot.

Located at 10901 US Hwy 84 E. The site is in a rural area where the U.S. Census American Community Survey 2023 five-year estimates for ZIP code 75954 report a population of about 2,976 and a median household income of $47,473. Housing in this area is predominantly owner-occupied, with a median owner-occupied home value of $87,300.

Cost and Timeline Context

The estimated cost of $975,000 is below the median estimated cost for similar additions to existing buildings in Shelby County, which is $2,000,000. The project size of 5,485 square feet is smaller than the county median of 8,150 square feet for comparable filings. The cost per square foot of $178 is close to the county median of $174 per square foot for this type of work.

The scheduled build window is 291 days, from August 2026 to June 2027. This duration is shorter than the county median build window of 456 days for similar projects. TDLR completed plan review in July 2026, and the status is listed as Review Complete. Construction is scheduled to finish in June 2027. GLS has registered six other projects with TDLR, totaling $36,180,100, including facilities in Livingston, Lufkin, and Wills Point.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75954 (Joaquin)

One email per change. Unsubscribe in one click. Privacy.

Joaquin ISD CTE is a Additions to Existing Building project located at 10901 US Hwy 84 E., Joaquin, TX 75954 in Joaquin, Texas. The project has an estimated value of $975K covering 5,485 sq ft. Joaquin ISD is the property owner and GLS is the design firm of record. The project was registered with TDLR on June 22, 2026.

Frequently Asked Questions

What is the total estimated cost of the Joaquin High School CTE project?

The estimated cost for the addition and renovation is $975,000. This figure is reported in the TDLR filing for the project registered in June 2026.

When is the construction scheduled to be completed?

Construction is scheduled to finish in June 2027. Work is planned to start in August 2026, following the completion of plan review in July 2026.

Who is the design firm for this project?

GLS is the design firm of record for the Joaquin ISD CTE project. The firm is listed in the TDLR registration documents for this specific addition and renovation.

Is the project located in a flood zone?

It is located in Zone X according to the FEMA National Flood Hazard Layer data for the site coordinates.

What is the scope of the work?

The scope includes the addition of a lobby to the existing CTE facility and a full renovation of the interior classrooms. This is classified as an addition to an existing building.

What is Joaquin ISD CTE?

Joaquin ISD CTE is a additions to existing building project at 10901 US Hwy 84 E. in Joaquin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Addition of lobby on existing CTE facility, full renovation of interior classrooms.

Is Joaquin ISD CTE open in Joaquin?

Joaquin ISD CTE is still under construction in Joaquin, TX, with an estimated completion of Jun 2027 according to its TDLR registration.

Where is Joaquin ISD CTE located?

Joaquin ISD CTE is located at 10901 US Hwy 84 E., Joaquin, TX, 75954, in Shelby County.

Who is the owner or developer of Joaquin ISD CTE?

Joaquin ISD is the property owner/developer of record for Joaquin ISD CTE, per its TDLR project registration.

Who is the architect or design firm for Joaquin ISD CTE?

GLS is the design firm of record for Joaquin ISD CTE, according to its TDLR filing.

How much does Joaquin ISD CTE cost and how big is it?

Joaquin ISD CTE has an estimated construction value of $975K and approximately 5,485 square feet (about $178/sqft), based on its TDLR filing.

Scope of Work

Addition of lobby on existing CTE facility, full renovation of interior classrooms.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

10901 US Hwy 84 E., Joaquin, TX, 75954

Loading location map…
31.96465, -94.03582