AUS02 is a new construction project at 1855 Bob White Road, Temple, in Bell County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Aug 2027. The project has an estimated value of $780.0M across about 500,000 sq ft.
- Estimated project value
- $780.0M
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 500,000 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $1.56K/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 1 year
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
3 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
35 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
364 days after the preceding date shown.
Source: TDLR filing
View source record
📰About AUS02
Rowan Digital Infrastructure is constructing a 500,000-square-foot data center facility at 1855 Bob White Road in Temple, Texas. The project, identified as AUS02 (Building 2), involves the new construction of a one-story steel frame structure with non-loading precast elements and a low-slope membrane roof system. This facility is designed to house data center storage and essential support spaces, representing a significant addition to the local infrastructure landscape in Bell County.
The estimated cost for this development is $780,000,000, which calculates to $1,560 per square foot. This figure is notably above the county median of $151 per square foot for similar new construction filings. The scheduled build window is 364 days, which is longer than the county median of 242 days. These metrics place the project in the top quarter for estimated cost within the 1,364 comparable new construction filings registered in Bell County.
Project Scope and Location
Located in the 76501 ZIP code, the site is in a community with a population of approximately 17,223 residents. The median household income in this area is estimated at $50,764, with a median owner-occupied home value of $151,000. The project is privately funded and situated on private land for private use. Third-party coverage, such as a post by ComingSoonTexas, has noted the massive scale of this new data center facility coming to Temple.
Paul J Glenn is the registered accessibility specialist of record for this project. The registration with the Texas Department of Licensing and Regulation occurred in July 2026, with construction starting in August 2026. The project status is registered, and plan review is pending. Completion is targeted for August 2027. This timeline aligns with the filed schedule, providing a clear window for the construction phase before the facility becomes operational.
For those tracking development in the region, this project stands out due to its size and cost relative to other local filings. The data center industry continues to expand in Texas, and this specific project in Temple reflects that growth. The detailed scope ensures that the structure meets the technical requirements for high-density storage and support operations, distinct from standard commercial buildings.
Project Registered
Project has been registered with TDLR and is in pre-construction phase
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 76501 (Temple)
One email per change. Unsubscribe in one click. Privacy.
AUS02 is a New Construction project located at 1855 Bob White Road, Temple, TX 76501 in Temple, Texas. The project has an estimated value of $780.0M covering 500,000 sq ft. Rowan Digital Infrastructure is the property owner. The project was registered with TDLR on July 24, 2026.
Frequently Asked Questions
What is the estimated cost of the AUS02 project?
The estimated cost is $780,000,000. This places the project above the county median for new construction filings in Bell County, reflecting its large scale and specialized data center requirements.
When is the construction expected to be completed?
The completion date on the filing is August 2027. The project was registered in July 2026, with construction starting in August 2026, and the work is targeted for August 2027.
Who is the owner or developer of the facility?
Rowan Digital Infrastructure is the owner and developer of record. The project is privately funded and located on private land for private use at 1855 Bob White Road in Temple.
What type of structure is being built?
It is a new construction of a one-story steel frame and non-loading precast building. It features a low-slope membrane roof system and is designed to house data center storage and facility support spaces.
Is the data center open to the public?
No, the project is under construction. The TDLR record shows the project is registered and under construction, with a completion target of August 2027. It is not yet operational.
What is AUS02?
AUS02 is a new construction project at 1855 Bob White Road in Temple, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: New construction of a 1 story steel frame and non-loading precast with low slope membrane roof system to support and house data center storage and facility support spaces.
Is AUS02 open in Temple?
AUS02 is still under construction in Temple, TX, with an estimated completion of Aug 2027 according to its TDLR registration.
Where is AUS02 located?
AUS02 is located at 1855 Bob White Road, Temple, TX, 76501, in Bell County.
Who is the owner or developer of AUS02?
Rowan Digital Infrastructure is the property owner/developer of record for AUS02, per its TDLR project registration.
How much does AUS02 cost and how big is it?
AUS02 has an estimated construction value of $780.0M and approximately 500,000 square feet (about $1.56K/sqft), based on its TDLR filing.
Scope of Work
New construction of a 1 story steel frame and non-loading precast with low slope membrane roof system to support and house data center storage and facility support spaces.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
1855 Bob White Road, Temple, TX, 76501
Watch all construction in 76501 (Temple)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Temple?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.