Project intelligenceTDLR TABS2026028030Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) in Dallas, TX

Various Locations, Dallas, TX, 75243

Opening ~Feb 2028Review Complete

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) is a renovation/alteration project at Various Locations, Dallas, in Dallas County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Feb 2028. The project has an estimated value of $402K across about 5,717 sq ft.

Estimated project value
$402K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,717 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$70/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
6 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 17, 2026533 days across supplied datesFeb 1, 2028

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    3 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    346 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    184 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About Traffic Signal Improvements (CSJ: 0918-47-491, etc.)

TxDOT District: Dallas is preparing to upgrade traffic infrastructure under the project name CSJ: 0918-47-491, etc. The filing, registered with TDLR in August 2026, covers 5,717 sq ft of work involving the installation of traffic signals, pedestrian elements, safety lighting, and pavement markings. Construction is scheduled to finish in February 2028, with work starting August 2027 following plan review completion in August 2026. The estimated cost for these various locations in Dallas, Texas, is $402,418.

The scope of work focuses on enhancing road safety through specific infrastructure improvements. The project includes the installation of new traffic signals and pedestrian components designed to manage flow and protect foot traffic. Safety lighting and updated pavement markings are also part of the renovation and alteration plan. This comprehensive approach aims to improve visibility and organization at the various sites within the Dallas 75243 area.

Project Scale and Cost Context

At $402,418, this project’s estimated cost is above the county median of $248,976 for similar renovation and alteration filings in Dallas County. The cost per square foot is $70, which is close to the county median of $72. The scheduled build window of 184 days is longer than the county median of 92 days, reflecting the multi-location nature of the work. TxDOT District: Dallas has six other registered projects totaling over $60 million, indicating a significant ongoing investment in regional infrastructure.

The design firm of record for this project is ESB, with Frank Fonseca listed as the registered accessibility specialist. The project involves public funds and is situated on public land. This environmental classification reduces flood-related construction risks. The registration status is Review Complete, confirming that plan review was finalized in August 2026.

Local Area and Labor Market

ZIP code 75243 has a population of about 63,907 and a median household income of $50,357, according to U.S. Census ACS 2023 five-year estimates. The area contains 31,577 housing units, with a median owner-occupied home value of $359,100. Housing in this ZIP code is predominantly renter-occupied. The Dallas County unemployment rate was 3.3 percent in July 2026, higher than a year earlier, which may influence local labor availability for the construction phase.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75243 (Dallas)

One email per change. Unsubscribe in one click. Privacy.

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) is a Renovation/Alteration project located at Various Locations, Dallas, TX 75243 in Dallas, Texas. The project has an estimated value of $402K covering 5,717 sq ft. TxDOT District: Dallas is the property owner and ESB is the design firm of record. The project was registered with TDLR on August 17, 2026.

Frequently Asked Questions

What is the primary scope of work for this project?

The project involves installing traffic signals, pedestrian elements, safety lighting, and pavement markings. This renovation and alteration work is designed to improve traffic flow and pedestrian safety across various locations in Dallas, Texas.

When is construction scheduled to start and finish?

Construction is scheduled to start in August 2027 and is scheduled to finish in February 2028. Plan review was completed in August 2026, clearing the path for the upcoming construction phase.

Who is the owner and design firm for this project?

The owner of record is TxDOT District: Dallas. The design firm of record is ESB. Frank Fonseca is listed as the registered accessibility specialist for the project.

Is the project site in a flood zone?

The coordinates place the project in zone X, indicating a lower flood risk for the construction and operation of the infrastructure.

How does the project cost compare to other Dallas County projects?

The estimated cost of $402,418 is above the county median of $248,976 for similar renovation and alteration filings. The cost per square foot is $70, which is close to the county median of $72.

What is Traffic Signal Improvements (CSJ: 0918-47-491, etc.)?

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) is a renovation/alteration project at Various Locations in Dallas, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Install traffic signals, pedestrian elements, safety lighting and pavement markings.

Is Traffic Signal Improvements (CSJ: 0918-47-491, etc.) open in Dallas?

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) is still under construction in Dallas, TX, with an estimated completion of Feb 2028 according to its TDLR registration.

Where is Traffic Signal Improvements (CSJ: 0918-47-491, etc.) located?

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) is located at Various Locations, Dallas, TX, 75243, in Dallas County.

Who is the owner or developer of Traffic Signal Improvements (CSJ: 0918-47-491, etc.)?

TxDOT District: Dallas is the property owner/developer of record for Traffic Signal Improvements (CSJ: 0918-47-491, etc.), per its TDLR project registration.

Who is the architect or design firm for Traffic Signal Improvements (CSJ: 0918-47-491, etc.)?

ESB is the design firm of record for Traffic Signal Improvements (CSJ: 0918-47-491, etc.), according to its TDLR filing.

How much does Traffic Signal Improvements (CSJ: 0918-47-491, etc.) cost and how big is it?

Traffic Signal Improvements (CSJ: 0918-47-491, etc.) has an estimated construction value of $402K and approximately 5,717 square feet (about $70/sqft), based on its TDLR filing.

Scope of Work

Install traffic signals, pedestrian elements, safety lighting and pavement markings.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Various Locations, Dallas, TX, 75243

32.90873, -96.73869

Watch all construction in 75243 (Dallas)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.