ServisFirst is a renovation/alteration project at 920 Memorial City Way, Suite 600, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Dec 2026. The project has an estimated value of $2.0M across about 13,327 sq ft.

Estimated project value
$2.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
13,327 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$150/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Aug 19, 2026131 days across supplied datesDec 28, 2026

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    21 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    19 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    91 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About ServisFirst

Colbolt is renovating 13,327 square feet of second-generation office space at 920 Memorial City Way, Suite 600, in Houston. The project, filed under the name ServisFirst, involves an interior renovation of the existing suite. TDLR records indicate the work is scheduled to finish in December 2026, with construction starting in September 2026.

MN Coxen LLC is the owner of record for this privately funded project on private land. Perrin Projects serves as the design firm of record. The estimated cost for the renovation is $2,000,000, which calculates to $150 per square foot. This figure is above the Harris County median of $80 per square foot for similar renovation and alteration filings. The total estimated cost also sits above the county median of $250,000 for this project type.

Project Status and Timeline

TDLR completed plan review in September 2026. The status is listed as Review Complete. Construction is scheduled to finish in December 2026, following a start date of September 2026. This results in a scheduled build window of 91 days, which is close to the Harris County median of 92 days for renovation projects. Brian Gary Stanton is the registered accessibility specialist for the project.

City of Houston permit records show two building permits on file at this street address, issued between March 2026 and June 2026. These permits describe high-rise office corridor remodels and areas of work. The ZIP code 77024 has a median household income of $142,039 and a median owner-occupied home value of $1,164,400, according to U.S. Census estimates.

Perrin Projects has six other TDLR-registered projects in Houston, totaling $4,808,312. These include projects at Woodbranch III, 910 Louisiana, 3737 Buffalo Speedway, Village Towers, and 777 At the Post Oak. The Harris County unemployment rate was 5.2 percent in July 2026. This renovation represents a significant investment in the Memorial City Way office corridor, focusing on updating the interior of the existing 13,327-square-foot space.

Review Complete

Design review complete, construction may proceed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77024 (Houston)

One email per change. Unsubscribe in one click. Privacy.

ServisFirst is a Renovation/Alteration project located at 920 Memorial City Way, Suite 600, Houston, TX 77024 in Houston, Texas. The project has an estimated value of $2.0M covering 13,327 sq ft. MN Coxen LLC is the property owner and Perrin Projects is the design firm of record. The project was registered with TDLR on August 19, 2026.

Frequently Asked Questions

What is the status of the Colbolt renovation?

TDLR completed plan review in September 2026. Construction started in September 2026 and is scheduled to finish in December 2026. The project is under Review Complete status.

How much does the Colbolt renovation cost?

The estimated cost is $2,000,000. This amount is above the Harris County median for renovation projects and equals $150 per square foot for the 13,327-square-foot space.

Who is the owner of the Colbolt project?

MN Coxen LLC is the owner of record. The project is privately funded and located on private land for private use at 920 Memorial City Way.

Is the Colbolt office open for business?

The TDLR record confirms construction is scheduled to finish in December 2026. It does not confirm that the business is open or operating.

Who is the design firm for the Colbolt renovation?

Perrin Projects is the design firm of record. They have several other registered projects in Houston, including renovations at Village Towers and 3737 Buffalo Speedway.

What is ServisFirst?

ServisFirst is a renovation/alteration project at 920 Memorial City Way, Suite 600 in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Interior renovation of existing 13,327SF second generation office space.

Is ServisFirst open in Houston?

ServisFirst is still under construction in Houston, TX, with an estimated completion of Dec 2026 according to its TDLR registration.

Where is ServisFirst located?

ServisFirst is located at 920 Memorial City Way, Suite 600, Houston, TX, 77024, in Harris County.

Who is the owner or developer of ServisFirst?

MN Coxen LLC is the property owner/developer of record for ServisFirst, per its TDLR project registration.

Who is the architect or design firm for ServisFirst?

Perrin Projects is the design firm of record for ServisFirst, according to its TDLR filing.

How much does ServisFirst cost and how big is it?

ServisFirst has an estimated construction value of $2.0M and approximately 13,327 square feet (about $150/sqft), based on its TDLR filing.

Scope of Work

Interior renovation of existing 13,327SF second generation office space.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

920 Memorial City Way, Suite 600, Houston, TX, 77024

29.78338, -95.53600

Related City Permits

Building permits found at or near this location

920 MEMORIAL CITY WAY FL 1, Houston, TX 77024

4,033 SF HI-RISE OFFICE CORRIDOR REMODEL 1-14-1-B-A '21 IBC SPK/FA

IssuedBuilding PmtJun 2026
HOU-26048283-BUILDINGPMT
920 MEMORIAL CITY WAY 900, Houston, TX 77024

HI-RISE OFFC RMODL 1946 SF AREA OF WORK 1-14-1-B-A-SPK-FA 2021 IBC

IssuedBuilding PmtMar 2026
HOU-26011421-BUILDINGPMT

Watch all construction in 77024 (Houston)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.