Project intelligenceTDLR TABS2027001595Renovation/Alteration
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction

Intersections at Tanner Road and at W Little York, Houston, TX, 77041

Opening ~Jun 2030Project Registered

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction is a renovation/alteration project at Intersections at Tanner Road and at W Little York, Houston, in Harris County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Under construction, estimated completion Jun 2030. The project has an estimated value of $256K across about 5,339 sq ft.

Estimated project value
$256K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
5,339 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$48/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3y 6mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Sep 21, 20261,349 days across supplied datesJun 1, 2030

3 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    102 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    1,247 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About BFH SEG2, W Sam Houston Tollway Widening and Reconstruction

The Harris County Toll Road Authority has filed a project to renovate and alter the W Sam Houston Tollway in Houston. The work, designated as BFH SEG2, focuses specifically on upgrading traffic signals and installing pedestrian ramps. The project site covers 5,339 sq ft at the intersections of Tanner Road and W Little York in the 77041 ZIP code.

This renovation is registered with the Texas Department of Licensing and Regulation (TDLR) under the accessibility program. The filing was submitted in September 2026, and the status remains Project Registered. Construction is scheduled to begin in January 2027, with the entire scope of work targeted for June 2030. This represents a scheduled build window of 1,247 days.

Project Scope and Design

AtkinsRealis serves as the design firm of record for this infrastructure improvement. The estimated cost for the project is $256,000. When divided by the 5,339 sq ft of affected area, this amounts to $48 per square foot. The scope is limited to accessibility and traffic control elements, specifically the installation of new pedestrian ramps and the update of traffic signal systems to ensure compliance and safety for all users.

The project involves public funds and public land, as is standard for roadway improvements managed by the Harris County Toll Road Authority. The owner of record is the Authority itself. Richard Todd Lozano is the registered accessibility specialist listed in the filing. The work is classified as a Renovation/Alteration, distinct from new ground-up construction, focusing on modifying existing infrastructure to meet current standards.

Local Context and Comparisons

The estimated cost of $256,000 is close to the Harris County median for similar renovation and alteration filings, which stands at $250,000. The per-square-foot cost of $48 is below the county median of $80 for comparable projects. However, the scheduled duration is significantly longer than the county median build window of 92 days. This extended timeline reflects the complexity of coordinating roadwork on a major tollway corridor in a dense urban environment.

The surrounding area in ZIP code 77041 has a population of approximately 33,180 people. The median household income in this area is estimated at $79,164, with a median owner-occupied home value of $269,000. The Harris County Toll Road Authority has four other TDLR-registered projects, including the East Aldine Camp and the NE EZ Tag Facility, indicating a broader portfolio of infrastructure management in the region.

Project Registered

Project has been registered with TDLR and is in pre-construction phase

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77041 (Houston)

One email per change. Unsubscribe in one click. Privacy.

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction is a Renovation/Alteration project located at Intersections at Tanner Road and at W Little York, Houston, TX 77041 in Houston, Texas. The project has an estimated value of $256K covering 5,339 sq ft. Harris County Toll Road Authority is the property owner and AtkinsRealis is the design firm of record. The project was registered with TDLR on September 21, 2026.

Frequently Asked Questions

What is being built on W Sam Houston Tollway?

The project involves renovating traffic signals and installing pedestrian ramps. It is a renovation and alteration project aimed at improving accessibility and traffic control at specific intersections.

Who is the owner of this project?

The Harris County Toll Road Authority is the owner and developer of record. AtkinsRealis is the design firm, and Richard Todd Lozano is the registered accessibility specialist.

When will construction start and finish?

Construction is scheduled to start in January 2027. The project is targeted for June 2030, following a registration date of September 2026.

How much does the project cost?

The estimated cost is $256,000. This covers the 5,339 sq ft of work, resulting in a cost of $48 per square foot.

Is the project currently open to the public?

The project is in the registration and planning phase. Construction has not yet begun, as it is scheduled to start in January 2027.

What is BFH SEG2, W Sam Houston Tollway Widening and Reconstruction?

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction is a renovation/alteration project at Intersections at Tanner Road and at W Little York in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Traffic signals and pedestrian ramps

Is BFH SEG2, W Sam Houston Tollway Widening and Reconstruction open in Houston?

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction is still under construction in Houston, TX, with an estimated completion of Jun 2030 according to its TDLR registration.

Where is BFH SEG2, W Sam Houston Tollway Widening and Reconstruction located?

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction is located at Intersections at Tanner Road and at W Little York, Houston, TX, 77041, in Harris County.

Who is the owner or developer of BFH SEG2, W Sam Houston Tollway Widening and Reconstruction?

Harris County Toll Road Authority is the property owner/developer of record for BFH SEG2, W Sam Houston Tollway Widening and Reconstruction, per its TDLR project registration.

Who is the architect or design firm for BFH SEG2, W Sam Houston Tollway Widening and Reconstruction?

AtkinsRealis is the design firm of record for BFH SEG2, W Sam Houston Tollway Widening and Reconstruction, according to its TDLR filing.

How much does BFH SEG2, W Sam Houston Tollway Widening and Reconstruction cost and how big is it?

BFH SEG2, W Sam Houston Tollway Widening and Reconstruction has an estimated construction value of $256K and approximately 5,339 square feet (about $48/sqft), based on its TDLR filing.

Scope of Work

Traffic signals and pedestrian ramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

Intersections at Tanner Road and at W Little York, Houston, TX, 77041

Loading location map…
29.85036, -95.56431