Home/Site Plans/West Travis County Public Utility Agency 1340 Transmission Main Segment A
Approved and Released

West Travis County Public Utility Agency 1340 Transmission Main Segment A

The applicant is proposing a Utility Line with asscciated improvements.

📍 12120-1/2 W US 290 HWY, AUSTIN, TX, 78737📄 Site Plan🏛️ SB 2038 ETJ RELEASE
Entitled100%
Timeline
Applied: Sep 20, 2016
Updated: Jan 21, 2022

Approved and Released

Step 5 of 5: Released ✓

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

📋Scope of Work

The applicant is proposing a Utility Line with asscciated improvements.

📅Entitlement Timeline

Application Filed
+30d
September 20, 2016
In Review
+364d
October 20, 2016
Approved
October 19, 2017

📍Location & Views

Open in MapsGet Directions|30.20936, -97.97221

🤝 Project Team

🏠 Owner Contact
C
Curtis D. Wilson
📝 Applicant Contact
R
robert ferguson
Murfee Engineering Company Inc./ Ronee Gilbert

Zoning & Land Use

Current Zoning
N/A
Existing Use
Vacant
Proposed Use
Utility Line

Environmental & Geographic

Watershed ClassBarton Springs Zone
🎓 School DistrictHAYS CONS. ISD
Traffic Impact Analysis
TIA Not Required

Case Manager

👤
Clarissa E. Davis
City of Austin Development Services

📌 Case Details

Case Number11602553
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2016-0436D
JurisdictionSB 2038 ETJ RELEASE
Property RSN5361002