Home/Site Plans/Austin Energy NW Substation Duct Bank

Site-plan research · Public application record

Approved and ReleasedDistrict 6

Austin Energy NW Substation Duct Bank

The applicant proposes installation of electric utility lines and all associated improvements.

7930-1/2 W PARMER LN, AUSTIN, TX, 78729 Site Plan AUSTIN FULL PURPOSE
Proposed units
Not supplied
About this figure

The unit count proposed in this site-plan record. It does not establish how many homes or spaces were completed.

Proposed floor area
Not supplied
About this figure

Proposed building floor area from the application. This is distinct from the land area of the site.

Gross site area
Not supplied
About this figure

The gross site acreage supplied in the application. It is not necessarily the developable or impervious area.

Application date
Nov 20, 2020
About this figure

The application date in the public record. Later milestones below show dated status changes when available.

Application history

Recorded site-plan milestones

Explore filed milestones and scheduled dates. Open a milestone for its source.

Nov 20, 2020220 days across supplied datesJun 28, 2021

3 timeline dates shown.

  1. Application Filed · AUSTIN site-plan record

    Source: AUSTIN site-plan record

    View source record
  2. In Review · AUSTIN site-plan record

    30 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record
  3. Approved · AUSTIN site-plan record

    190 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record

Site Plan Metrics

FAR:—
Impervious:5.9%
Applied:Nov 20, 2020
Approved:Jun 28, 2021

Approved and Released

Step 5 of 5: Released ✓

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

Scope of Work

The applicant proposes installation of electric utility lines and all associated improvements.

Location & views

7930-1/2 W PARMER LN, AUSTIN, TX, 78729

Loading location map…
30.46031, -97.75335

🤝 Project Team

📝 Applicant Contact
📝
Garza EMC

Fees

Tree Mitigation Fee
$73,500.00
Outstanding
Environmental Inspection (deposit)
$4,347.00
Outstanding
Technology Surcharge-DSD
$173.88
Outstanding
Basic Notification
$291.00
Outstanding
City Arborist Site Plan/Subdivision Review
$3,668.84
Outstanding
UDS Engineering Plan Review
$228.75
Outstanding
Utility & Storm Sewers-DSD
$6,324.00
Outstanding
PARD-Site Plan/Subdivision Review Fee
$717.00
Outstanding
Technology Surcharge-DSD
$411.35
Outstanding
Completeness Check Fee
$406.00
Outstanding
WPD-Site Plan Completeness Check
$34.00
Outstanding
Technology Surcharge-DSD
$17.60
Outstanding

Zoning & Land Use

Current Zoning
na
Existing Use
Industrial
Proposed Use
Utility Line

Environmental & Geographic

Watershed ClassSuburban Watershed
School DistrictAUSTIN ISD
Impervious Cover5.9%

Case Manager

Rosemary Avila
City of Austin Development Services

Explore Area

AUSTIN
Directory by city
ZIP 78729
Projects in this ZIP
Council District 6
From site plan record

Case Details

Case Number12592572
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2020-0421D
JurisdictionAUSTIN FULL PURPOSE
TCAD IDR379614
Property RSN6080360

Related Cases

Legal Description

REFERENCE ONLY - S7227 - Motorola Parmer Lane Sub Amd , Block A, Lot 1, aka MOTOROLA NW CONDO, ACRES 128.816, COMMON INT, (REF)