Home/Site Plans/North Fork Dry Creek Wastewater Interceptor, Segment 3 Phase B
Approved and Released#12653923District 2

North Fork Dry Creek Wastewater Interceptor, Segment 3 Phase B

The applicant proposes 383 LF OF 12¿ GRAVITY WASTEWATER PIPELINE AND 1,851 LF OF 24¿ GRAVITY WASTEWATER PIPELINE, MANHOLES, AND APPURTENANCES BEGINNING AT MH 7 OF NORTHFORK 3 GRAVITY WASTEWATER PIPELINE PHASE A 437' NW OF FM 1625 AND 2561' SW OF FINIAL DR AND ENDING 104' SE OF THE PROPOSED INTERSECTION OF SLAUGHTER LN AND FM1625.

📍 7736-1/2 FM 1625 RD, AUSTIN, TX, 78744📄 Site Plan🏛️ AUSTIN LTD
Entitled100%
Units
Density:
Building
FAR:
Site area
City: AUSTIN
Dates
Applied: Mar 11, 2021
Updated: May 10, 2024

📊Site Plan Metrics

#12653923
Proposed Units
Building Size
Site Area
Density
FAR:
Applied:Mar 11, 2021
Approved:Sep 9, 2022

Approved and Released

Site plan approved and released. Ready for permit issuance.

📋Scope of Work

The applicant proposes 383 LF OF 12¿ GRAVITY WASTEWATER PIPELINE AND 1,851 LF OF 24¿ GRAVITY WASTEWATER PIPELINE, MANHOLES, AND APPURTENANCES BEGINNING AT MH 7 OF NORTHFORK 3 GRAVITY WASTEWATER PIPELINE PHASE A 437' NW OF FM 1625 AND 2561' SW OF FINIAL DR AND ENDING 104' SE OF THE PROPOSED INTERSECTION OF SLAUGHTER LN AND FM1625.

📅Entitlement Timeline

Application Filed
March 11, 2021
Approved
September 9, 2022

📍Location & Views

Open in MapsGet Directions|30.14515, -97.70046

Zoning & Land Use

Current Zoning
PUD - PLANNED UNIT DEVELOPMENT
Existing Use
Vacant
Proposed Use
Utility Line

Environmental & Geographic

Watershed ClassSuburban Watershed
🎓 School DistrictDEL VALLE ISD

Case Manager

👤
Carlos Huizar
City of Austin Development Services

Explore Area

🏙️
AUSTIN
Directory by city
📮
ZIP 78744
Projects in this ZIP
🏛️
Council District 2
From site plan record

📌 Case Details

Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-2021-0061D
JurisdictionAUSTIN LTD
TCAD ID0348110701
Property RSN6095898

🔗 Related Cases