Home/Site Plans/MADRONE HILL SUBDIVISION WATERLINE

Site-plan research · Public application record

Approved and Released

MADRONE HILL SUBDIVISION WATERLINE

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

TRAIL OF MADRONES, AUSTIN, TX Site Plan
Proposed units
Not supplied
About this figure

The unit count proposed in this site-plan record. It does not establish how many homes or spaces were completed.

Proposed floor area
Not supplied
About this figure

Proposed building floor area from the application. This is distinct from the land area of the site.

Gross site area
Not supplied
About this figure

The gross site acreage supplied in the application. It is not necessarily the developable or impervious area.

Application date
Jun 12, 1990
About this figure

The application date in the public record. Later milestones below show dated status changes when available.

Application history

Recorded site-plan milestones

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jun 12, 19906,107 days across supplied datesMar 2, 2007

3 timeline dates shown.

  1. Application Filed · AUSTIN site-plan record

    Source: AUSTIN site-plan record

    View source record
  2. In Review · AUSTIN site-plan record

    30 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record
  3. Approved · AUSTIN site-plan record

    6,077 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record

Approved and Released

Step 5 of 5: Released ✓

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

Location & views

TRAIL OF MADRONES, AUSTIN, TX

30.31593, -97.79649

🤝 Project Team

🏠 Owner Contact
W
Wayne Spencer

Case Manager

Unknown
City of Austin Development Services

Case Details

Case Number151577
Case TypeSite Plan
Sub Type—
Permit NumberSP-90-0111DS
Jurisdiction—
Property RSN8024