Home/Site Plans/93-94 MISC. PIPE REPLACEMENTS GROUP ONE

Site-plan research · Public application record

Approved and Released

93-94 MISC. PIPE REPLACEMENTS GROUP ONE

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

E 38TH ST, AUSTIN, TX Site Plan
Proposed units
Not supplied
About this figure

The unit count proposed in this site-plan record. It does not establish how many homes or spaces were completed.

Proposed floor area
Not supplied
About this figure

Proposed building floor area from the application. This is distinct from the land area of the site.

Gross site area
Not supplied
About this figure

The gross site acreage supplied in the application. It is not necessarily the developable or impervious area.

Application date
Oct 28, 1993
About this figure

The application date in the public record. Later milestones below show dated status changes when available.

Application history

Recorded site-plan milestones

Explore filed milestones and scheduled dates. Open a milestone for its source.

Oct 28, 19934,873 days across supplied datesMar 2, 2007

3 timeline dates shown.

  1. Application Filed · AUSTIN site-plan record

    Source: AUSTIN site-plan record

    View source record
  2. In Review · AUSTIN site-plan record

    30 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record
  3. Approved · AUSTIN site-plan record

    4,843 days after the preceding date shown.

    Source: AUSTIN site-plan record

    View source record

Approved and Released

Step 5 of 5: Released ✓

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

Location & views

E 38TH ST, AUSTIN, TX

30.29965, -97.73170

🤝 Project Team

🏠 Owner Contact

Case Manager

Javad Oskouipour
City of Austin Development Services

Case Details

Case Number153196
Case TypeSite Plan
Sub Type
Permit NumberSP-93-0477DS
Jurisdiction
Property RSN9004