β
Approved and Released
GARDENS AT BALCONES, THE
Site plan fully approved and released. All conditions cleared. Ready for construction permitting.
π SPICEWOOD PKWY, AUSTIN, TXπ Site Plan
Entitled100%
Timeline
Applied: Oct 11, 1999
Updated: Mar 2, 2007
β
Approved and Released
Step 5 of 5: Released βSite plan fully approved and released. All conditions cleared. Ready for construction permitting.
Next:Pull building permits to begin construction.
π Entitlement Timeline
Application Filed
+30dOctober 11, 1999
In Review
+2669dNovember 10, 1999
Approved
March 2, 2007
Active
February 16, 2000
π€ Project Team
π Owner Contact
L
Land Creek Development
Land Creek Development
π Applicant Contact
A
Aaron Pesek
Garrett-Ihnen Civil Engineers, Inc
π Nearby Site Plans
LAUREL MOUNTAIN ELEMENTARY SCHOOL
Approved and Released β’ AUSTIN β’ Mar 2, 2007
NORTHWEST HILLS RANCH III
Approved and Released β’ AUSTIN β’ Mar 2, 2007
CANYON MESA PHASE 1 SLOPE PROTECTION IMPROVEMENTS
Approved and Released β’ AUSTIN β’ Mar 2, 2007
LIFT STATION NO. 3-ACCESS DRIVEWAY
Approved and Released β’ AUSTIN β’ Mar 2, 2007
DAVID & TINA SMITH RESIDENCE
Approved and Released β’ AUSTIN β’ Mar 2, 2007
HALLMARK BAPTIST CHURCH
Approved and Released β’ AUSTIN β’ Mar 2, 2007
HALLMARK BAPTIST CHURCH
Approved and Released β’ AUSTIN β’ Mar 2, 2007
HALLMARK BAPTIST CHURCH
Closed β’ AUSTIN β’ Mar 2, 2007
$Bull Creek - Old Lampasas #3 Dam Modernization
Approved and Released β’ AUSTIN β’ May 15, 2024
NPC OFFSITE WASTEWATER IMPROVEMENTS LIFT STATION & FORCE MAIN
Closed β’ AUSTIN β’ Mar 2, 2007
OVERLOOK AT BULL CREEK
Approved and Released β’ AUSTIN β’ Mar 2, 2007
NPC OFFSITE WASTEWATER IMPROVEMENTS 21" WASTEWATER INTERCEPTOR
Closed β’ AUSTIN β’ Mar 2, 2007
Key Stakeholders
Zoning & Land Use
Current Zoning
SF-6
Case Manager
π€
Don Gipson
City of Austin Development Services
Explore Area
π Case Details
Case Number162340
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-99-2119C
Jurisdictionβ
Property RSN7380