Home/Site Plans/ZACHARY SCOTT SUBDIVISION WASTEWATER IMPROVEMENTS (SITE PLAN REVISION #2)
βœ… Approved and Released

ZACHARY SCOTT SUBDIVISION WASTEWATER IMPROVEMENTS (SITE PLAN REVISION #2)

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

πŸ“ RIVER PLANTATION DR, AUSTIN, TXπŸ“„ Site Plan
Entitled100%
Timeline
Applied: Jan 8, 2007
Updated: Feb 26, 2008
βœ…

Approved and Released

Step 5 of 5: Released βœ“

Site plan fully approved and released. All conditions cleared. Ready for construction permitting.

Next:Pull building permits to begin construction.

πŸ“…Entitlement Timeline

Application Filed
+30d
January 8, 2007
In Review
+384d
February 7, 2007
Approved
February 26, 2008

πŸ“Location & Views

Open in MapsGet Directions|30.14403, -97.78157

🀝 Project Team

🏠 Owner Contact
B
Bryan Sims
Lennar Buffington Colo Cross, Lp
πŸ“ Applicant Contact
L
LAUREN POWELL
LJA Engineering & Surveying, Inc

Zoning & Land Use

Current Zoning
SF-4
Existing Use
999
Proposed Use
999

Environmental & Geographic

πŸ’§ WatershedRinard Creek
Watershed ClassSuburban Watershed

Case Manager

πŸ‘€
Chris Yanez
City of Austin Development Services

πŸ“Œ Case Details

Case Number280958
Case TypeSite Plan
Sub TypeSite Plan Administrative
Permit NumberSP-05-0033D
Jurisdictionβ€”
Property RSN6583