📋 Solicitation✅ Posted
SH 218: 0465-01-067; RH
480 days leftDue: November 2, 2027
📄Description
Section 130 Program, SH 218 near FM 78, DOT 764352R, Rail Signal Preemption
Type of Work: Railroad Crossing Improvements
Highway: SH 218
Location: SH 218 (Pat Booker Rd) to At UPRR
County: Bexar
Working Days: 180.0
Oversight: State
Spec Book Year: 2024.0
🚧TxDOT Project Details
💲Estimated Cost
$540K
Engineer's estimate / low bid estimate from TxDOT
Key Details
- Solicitation ID
- txdot_0465-01-067
- Source
- TxDOT
- Status
- ✅ Posted
- Open for submissions
- Category
- mechanical electrical
- Due Date
- November 2, 2027
👤 Contact
Dale Picha
[email protected]🏛️ Agency
TxDOT - San Antonio District
🏛️ State Agency
Bexar, TX
Agency #txdot_san_antonio
View agency profile →View all TxDOT - San Antonio District bids →View the official TxDOT project data
View on data.texas.gov