Permitted

Intersection Capacity Improvements (FY 23) - CIP ST2303

3 Intersections, Mckinney, TX 75072, Mckinney (Collin County)

TDLR Project: 1

Source coverage

1 linked record

Explore the filings behind this project.

How these records are linked

Record matching confidence: 55%. This describes the record association, not construction completion.

Reported project value
$300K
About this figure

The value recorded for this linked project. Filings may describe overlapping scopes, so this is not a final invoice or an appraisal.

Reported floor area
Not supplied
About this figure

Floor area associated with the linked project record. Open the source records to inspect each reported scope.

Site area
Not supplied
About this figure

The count or area provided by the linked records. Proposed figures may change as plans are revised.

Last recorded activity
Oct 8, 2026
About this figure

The latest activity date in this linked project record. It does not establish current work at the site.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Sep 1, 2026456 days across supplied datesDec 1, 2027

3 timeline dates shown.

  1. Construction Start · Scheduled date

    Projected start

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR Project · TABS2027003140

    View source record
  2. TDLR Project: Intersection Capacity Improvements (FY 23) - CIP ST2303 · TDLR Project · TABS2027003140

    Project Registered

    37 days after the preceding date shown.

    Source: TDLR Project · TABS2027003140

    View source record
  3. Expected Completion · Scheduled date

    Projected completion

    A date supplied in the filing; this does not confirm that work started or finished.

    419 days after the preceding date shown.

    Source: TDLR Project · TABS2027003140

    View source record

Project Metrics

TDLR #TABS2027003140
$300K
Total Value
Started:Oct 8, 2026
Last activity:Oct 8, 2026
Duration:—

Location & views

3 Intersections, Mckinney, TX 75072

33.18949, -96.73434
Detailed source chronology
2026
Sep 1
2 mos ago
Construction Start
TDLR Project • Projected start
Work itemIntersection Capacity Improvements (FY 23) - CIP ST2303
Start Sep 1, 2026→End Dec 1, 2027
Open record
September 1, 2026
TABS2027003140
2026
Oct 8
11 days ago
TDLR Project: Intersection Capacity Improvements (FY 23) - CIP ST2303
TDLR Project • Project Registered
Valuation: $300K
Link confidence: 100%
Open record
October 8, 2026
TABS2027003140
2027
Dec 1
1 yr from now
Expected Completion
TDLR Project • Projected completion
Work itemIntersection Capacity Improvements (FY 23) - CIP ST2303
Start Sep 1, 2026→End Dec 1, 2027
Open record
December 1, 2027
TABS2027003140

Linked records by source

TDLR Projects (1)

Public source records
Intersection Capacity Improvements (FY 23) - CIP ST2303
Project Registered • Oct 8, 2026
TABS2027003140
Description: Sidewalks and trails (~12,500 SF), pedestrian ramps, and pavement markings
Facility: Intersection
Design firm: CobbFendley
Estimated cost: $300K
Sq Ft: 12,500