๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

ORANGE RIVERFRONT BOARDWALK & PAVILION

6TH & WEST DIVISION, Orange, TX 77630, Orange, TX, 77630
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB1813456
$7.4M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2y 5mo
Duration
Registered:Jun 10, 2011
Start:Aug 1, 2011
Target:Dec 30, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Riverfront stabalization and boardwalk. New outdoor pavilion with shade structures and support buildings.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 10, 2011
Construction Start
August 1, 2011
Expected Completion
December 30, 2013