๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

CEFCO CONVENIENCE STORES - FM 2305

FM 2305 @ HILLIARD DRIVE, Temple, TX 76504, Temple, TX, 76504
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2804721
$850K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Dec 9, 2011
Start:Jan 1, 2012
Target:May 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Concrete paving, steel framing, interior finish, gyp board, paint, EIFS and masonry.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 9, 2011
Construction Start
January 1, 2012
Expected Completion
May 1, 2012