๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MOSS LAKE WATER TREATMENT PLANT EXPANSIO

209 NORTH LAKE DR., Gainesville, TX 76240, Gainesville, TX, 76240
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3805093
$260K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 2mo
Duration
Registered:Dec 7, 2012
Start:Apr 1, 2013
Target:Jun 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Operations Building for existing water treatment plant,appropriately 970 square feet, to include two offices, a

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 7, 2012
Construction Start
April 1, 2013
Expected Completion
June 1, 2014