HILL 'N DALE STREET RECONSTRUCTION

SHERWOOD BTWN JOSEY & PERRY, Carrollton, TX 75006, Carrollton, TX, 75006
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3805456
$543K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 year
Duration
Registered:Dec 14, 2012
Start:Jan 1, 2013
Target:Jan 1, 2014
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Replace sidewalks, barrier free ramps, curbs, sanitary sewer.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 14, 2012
Construction Start
January 1, 2013
Expected Completion
January 1, 2014