Project intelligenceTDLR EABPRJB5811542New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

MUD W-3 WATER TREATMENT PLANT in Lakeway, TX

4105 LAKEWAY BLVD., Lakeway, TX, 78704

Construction complete · Nov 2015Project Closed

MUD W-3 WATER TREATMENT PLANT is a new construction project at 4105 LAKEWAY BLVD., Lakeway, in Travis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Nov 2015). The project has an estimated value of $2.0M.

Estimated project value
$2.0M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
Not supplied
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
—
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
8 months
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Mar 1, 2015245 days across supplied datesNov 1, 2015

4 timeline dates shown.

  1. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Source: TDLR filing

    View source record
  2. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    10 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    235 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 78704 (Lakeway)

One email per change. Unsubscribe in one click. Privacy.

MUD W-3 WATER TREATMENT PLANT is a New Construction project located at 4105 LAKEWAY BLVD., Lakeway, TX 78704 in Lakeway, Texas. The project has an estimated value of $2.0M. LAKEWAY MUNICIPAL UTILITY DISTRICT is the property owner and CASTLEBERRY ENGINEERING AND CONSULTING is the design firm of record. The project was registered with TDLR on March 11, 2015.

Frequently Asked Questions

What is MUD W-3 WATER TREATMENT PLANT?

MUD W-3 WATER TREATMENT PLANT is a new construction project at 4105 LAKEWAY BLVD. in Lakeway, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construct a new pump station and associated piping.

Is MUD W-3 WATER TREATMENT PLANT open in Lakeway?

Construction on MUD W-3 WATER TREATMENT PLANT is complete — TDLR records show the project passed its required accessibility inspection in Nov 2015. The building is finished and very likely open.

Where is MUD W-3 WATER TREATMENT PLANT located?

MUD W-3 WATER TREATMENT PLANT is located at 4105 LAKEWAY BLVD., Lakeway, TX, 78704, in Travis County.

Who is the owner or developer of MUD W-3 WATER TREATMENT PLANT?

LAKEWAY MUNICIPAL UTILITY DISTRICT is the property owner/developer of record for MUD W-3 WATER TREATMENT PLANT, per its TDLR project registration.

Who is the architect or design firm for MUD W-3 WATER TREATMENT PLANT?

CASTLEBERRY ENGINEERING AND CONSULTING is the design firm of record for MUD W-3 WATER TREATMENT PLANT, according to its TDLR filing.

How much does MUD W-3 WATER TREATMENT PLANT cost and how big is it?

MUD W-3 WATER TREATMENT PLANT has an estimated construction value of $2.0M, based on its TDLR filing.

Scope of Work

Construct a new pump station and associated piping.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

4105 LAKEWAY BLVD., Lakeway, TX, 78704

Loading location map…
30.36152, -98.00546

Related City Permits

Building permits found at or near this location

4105 TRIPLE CROWN
12.36 mi away

2 bathrooms getting remodeled kitchen flooring and painting throughout. Replace back patio door

FinalMechanical PermitAddition and RemodelOct 2026
View Details
2026-126517 MP
Titan HVAC Services LLC
4105 TRIPLE CROWN
12.36 mi away

2 bathrooms getting remodeled kitchen flooring and painting throughout. Replace back patio door

FinalElectrical PermitAddition and RemodelOct 2026
View Details
2026-126517 EP
BLUE DIAMOND MEP LTD CO
4105 MC BRINE PL
13.72 mi away

ePlan: Residential Expedited Review - Addition and Remodel to Existing Single Family Res. work to include remodel of existing garage into living space with a bedroom hallway addition of covd patio connecting to new 2-story 2-car structure with a studio above

ActiveMechanical PermitAddition and RemodelNov 2026
View Details
2026-124062 MP
Space City Air Conditioning Systems, LLC
4105 MC BRINE PL
13.72 mi away

ePlan: Residential Expedited Review - Addition and Remodel to Existing Single Family Res. work to include remodel of existing garage into living space with a bedroom hallway addition of covd patio connecting to new 2-story 2-car structure with a studio above

ActivePlumbing PermitAddition and RemodelOct 2026
View Details
2026-124062 PP
Mustang Plumbing
4105 MC BRINE PL
13.72 mi away

ePlan: Residential Expedited Review - Addition and Remodel to Existing Single Family Res. work to include remodel of existing garage into living space with a bedroom hallway addition of covd patio connecting to new 2-story 2-car structure with a studio above

ActiveElectrical PermitAddition and RemodelOct 2026
View Details
2026-124062 EP
In Charge Electrical Services, LLC

Watch all construction in 78704 (Lakeway)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.