๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

DUCK POND-EAST

NE CRN BIRD'S FT TRL & COBALT 32.805643, -97.086438, Arlington, TX 76005, Arlington, TX, 76005
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8805354
$296K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Nov 20, 2017
Start:Dec 1, 2017
Target:May 1, 2018
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

The project includes the construction of an 8' wide recreational concrete trail with adjacent seating and landsc

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 20, 2017
Construction Start
December 1, 2017
Expected Completion
May 1, 2018