๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Harmony School of Innovation - Waco Classroom Conversion

1110 South Valley Mills Road, Beverly Hills, TX 76711, Beverly Hills, TX, 76711
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019006656
$300K
Project Value
6,000
Square Feet
$50/sqft
Cost/SqFt
2 months
Duration
Registered:Mar 11, 2019
Start:Jun 3, 2019
Target:Aug 15, 2019
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Turn existing gym into classrooms

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 11, 2019
Project Closed
August 15, 2019
Construction Start
June 3, 2019
Expected Completion
August 15, 2019

๐Ÿ“Location & Views

Open in MapsGet Directions|31.52607, -97.14860

Get alerts for McLennan

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists