Project intelligenceTDLR TABS2019009885New Construction
Funding type

This project involves public funds, public land, or is a Federally funded roadway project.

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.

7600 KOEBLEN RD, RICHMOND TX, 77469, Rosenberg, TX, 77469

Construction complete · Jul 2021Project Closed

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. is a new construction project at 7600 KOEBLEN RD, RICHMOND TX, 77469, Rosenberg, in Fort Bend County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jul 2021). The project has an estimated value of $127.8M across about 374,480 sq ft.

Estimated project value
$127.8M
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
374,480 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$341/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
2y 1mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Apr 22, 2019801 days across supplied datesJul 1, 2021

4 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    40 days after the preceding date shown.

    Source: TDLR filing

    View source record
  3. Project closed · TDLR filing

    The project record was closed in TDLR.

    761 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record

📰About NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.

Lamar Consolidated ISD completed the new construction of Dr. Thomas E. Randle High School in Rosenberg, Texas. The project, filed with the Texas Department of Licensing and Regulation (TDLR) as NEW High School for the Lamar Consolidated Independent School District, involved a 374,480 sq ft facility at 7600 Koeblen Rd, Richmond, TX 77469. With an estimated cost of $127,750,000, the development represents a significant investment in the local educational infrastructure of Fort Bend County.

PBK Architects Inc served as the design firm of record for this large-scale build. The project was registered with TDLR in April 2019, with construction officially beginning in June of that same year. The scheduled build window spanned 761 days, a period significantly longer than the 202-day median for new construction filings in the county. The final estimated cost per square foot was $341, which sits above the county median of $100 per square foot for similar projects.

Project Status and Financial Context

TDLR closed the project file in July 2021, marking the conclusion of the accessibility review process for this construction. This date aligns with the completion date listed on the original filing. While the TDLR record confirms the end of the regulatory review, it does not provide details on the school’s operational status or opening date. The project utilized public funds and was situated on public land, reflecting its role as a district-owned facility.

In the context of other work by Lamar Consolidated ISD, this high school stands out for its scale. The district has six other TDLR-registered projects totaling $41,713,161, including a $30,900,000 administration building in Rosenberg and various elementary school projects in Richmond. PBK Architects Inc has also designed other major facilities, such as a $62,000,000 junior high school in Rosenberg, demonstrating a pattern of large-scale educational and civic development in the region.

The surrounding area, ZIP code 77469, has a population of approximately 65,159 residents according to U.S. Census ACS 2023 estimates. The median household income in this area is $101,546, with a median owner-occupied home value of $315,000. These demographic figures provide a backdrop for the substantial investment in educational infrastructure made by the school district in this community.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 77469 (Rosenberg)

One email per change. Unsubscribe in one click. Privacy.

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. is a New Construction project located at 7600 KOEBLEN RD, RICHMOND TX, 77469, Rosenberg, TX 77469 in Rosenberg, Texas. The project has an estimated value of $127.8M covering 374,480 sq ft. Lamar Consolidated ISD is the property owner and PBK Architects Inc is the design firm of record. The project was registered with TDLR on April 22, 2019.

Frequently Asked Questions

What is the current status of the construction project?

TDLR closed the project file in July 2021. This indicates that the accessibility review process for the new high school construction was completed at that time.

Who was the design firm for the new high school?

PBK Architects Inc was the design firm of record for the new 2000-student high school in Rosenberg, Texas.

Where is the new high school located?

The facility is located at 7600 Koeblen Rd, Richmond, TX 77469, which is in the Rosenberg area of Fort Bend County.

Is the school open for enrollment?

The TDLR record only confirms the closure of the project file in July 2021. It does not provide information regarding the school's operational status or enrollment dates.

What is NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.?

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. is a new construction project at 7600 KOEBLEN RD, RICHMOND TX, 77469 in Rosenberg, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: NEW 2000 STUDENT HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.

Is NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. open in Rosenberg?

Construction on NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. is complete — TDLR records show the project passed its required accessibility inspection in Jul 2021. The building is finished and very likely open.

Where is NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. located?

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. is located at 7600 KOEBLEN RD, RICHMOND TX, 77469, Rosenberg, TX, 77469, in Fort Bend County.

Who is the owner or developer of NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.?

Lamar Consolidated ISD is the property owner/developer of record for NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT., per its TDLR project registration.

Who is the architect or design firm for NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.?

PBK Architects Inc is the design firm of record for NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT., according to its TDLR filing.

How much does NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. cost and how big is it?

NEW HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT. has an estimated construction value of $127.8M and approximately 374,480 square feet (about $341/sqft), based on its TDLR filing.

Scope of Work

NEW 2000 STUDENT HIGH SCHOOL FOR THE LAMAR CONSOLIDATED INDEPENDENT SCHOOL DISTRICT.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

7600 KOEBLEN RD, RICHMOND TX, 77469, Rosenberg, TX, 77469

Location by street address

Watch all construction in 77469 (Rosenberg)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.

Keep exploring

What else is changing in Rosenberg?

See the surrounding filings, compare the reported schedules, and follow the places that matter to you.