๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Coppell Fire Station #4

440 Northpoint Drive, Coppell, TX 75019, Coppell, TX, 75019
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020000545
$7.4M
Project Value
19,275
Square Feet
$384/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Sep 10, 2019
Start:Nov 1, 2019
Target:Nov 30, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New fire station and fire department storage

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 10, 2019
Project Closed
November 30, 2020
Construction Start
November 1, 2019
Expected Completion
November 30, 2020