๐Review Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Upland Ave
66th St to 82nd St, Lubbock, TX 79424, Lubbock, TX, 79424
Construction50%
๐Project Metrics
TDLR #TABS2020021096$9.3M
Project Value
93,687
Square Feet
$99/sqft
Cost/SqFt
3y 4mo
Duration
Registered:Jul 24, 2020
Start:May 1, 2022
Target:Aug 8, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Widening, concrete paving, hot mix, sidewalk, ramps, driveways, structures, traffic signals, lighting, signing, striping
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 24, 2020
Review Complete
July 24, 2020
Construction Start
May 1, 2022
Expected Completion
August 8, 2025
๐Related Projects
๐Nearby Projects
Within 1 kmAction Behavior Center Lubbock Regal Park - Phase II
5815 82nd St., Suite 115, Lubbock, TX 79424ยท$150K
Action Behavior Center Lubbock 82nd St.
5815 82nd Street Suite 120, Lubbock, TX 79424ยท$250K
Kung Fu Tea Lubbock
5815 82ND ST, Suite 150, Lubbock, TX 79424ยท$150K
Thacker Jewelry - Building Addition
6120 82nd St, Lubbock, TX 79424ยท$75K
Property Owner
๐ค
TxDOT District: Lubbock
Contact: Michael Wittie, P.E.
4 projects ยท $25.8M
View company profile