Project intelligenceTDLR TABS2020021423Additions to Existing Building
Funding type

This project is privately funded, on private land for private use.

NTMWD Muddy Creek Administration Building Improvement and Expansion in Wylie, TX

5400 Pleasant Valley Road, Wylie, TX, 75098

Construction complete · Sep 2026Project Closed

NTMWD Muddy Creek Administration Building Improvement and Expansion is a additions to existing building project at 5400 Pleasant Valley Road, Wylie, in Taylor County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Sep 2026). The project has an estimated value of $974K across about 3,968 sq ft.

Estimated project value
$974K
About this figure

Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.

Reported floor area
3,968 ft²
About this figure

Square footage reported for this scope of work. It may cover only part of a larger property.

Estimated cost / ft²
$245/sqft
About this figure

Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.

Scheduled duration
3y 10mo
About this figure

The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.

The project record

Project timeline

Explore filed milestones and scheduled dates. Open a milestone for its source.

Jul 30, 20202,242 days across supplied datesSep 19, 2026

6 timeline dates shown.

  1. Project registered · TDLR filing

    Registration of the project with the Texas Department of Licensing and Regulation.

    Source: TDLR filing

    View source record
  2. Review complete · TDLR filing

    The filing records completion of the accessibility review.

    Same day as the preceding date shown.

    Source: TDLR filing

    View source record
  3. Scheduled construction start · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    63 days after the preceding date shown.

    Source: TDLR filing

    View source record
  4. Scheduled completion · Scheduled date

    A date supplied in the filing; this does not confirm that work started or finished.

    1,369 days after the preceding date shown.

    Source: TDLR filing

    View source record
  5. Inspection complete · TDLR filing

    The filing records completion of the accessibility inspection.

    552 days after the preceding date shown.

    Source: TDLR filing

    View source record
  6. Project closed · TDLR filing

    The project record was closed in TDLR.

    258 days after the preceding date shown.

    Source: TDLR filing

    View source record

📰About NTMWD Muddy Creek Administration Building Improvement and Expansion

The North Texas Municipal Water District completed a $973,558 expansion of its Muddy Creek Operations Building at 5400 Pleasant Valley Road in Wylie. This project, filed as the NTMWD Muddy Creek Administration Building Improvement and Expansion, added 3,968 square feet of new space to the existing facility. The construction concluded with a final inspection passed in January 2026, and the Texas Department of Licensing and Regulation closed the project file in September 2026.

The scope of work focused on improving the existing operations facility by adding locker rooms, a break room, and updated utilities. A new breezeway connects the original structure to the expansion, creating a continuous workflow for staff. The project was privately funded on private land for private use, reflecting the district’s internal infrastructure needs rather than a public-facing retail or commercial development.

Project Specifications and Cost

With an estimated cost of $973,558 for 3,968 square feet, the project averaged $245 per square foot. This figure is above the county median of $173 per square foot for similar additions to existing buildings in Taylor County. The scheduled build window was 1,369 days, which is longer than the county median of 214 days for this type of construction. The extended timeline likely reflects the complexity of integrating new utilities and structural connections into an active water district facility.

Huitt-Zollars, Inc. served as the design firm of record for the project. The firm has registered six other projects with TDLR, totaling $11,505,566, including work in Fort Worth, Houston, Weslaco, Anna, and El Paso. The North Texas Municipal Water District, the owner of record, has six other TDLR-registered projects totaling $41,312,878, including the Wylie Service Center and the Shiloh Pump Station in Richardson.

The project was registered with TDLR in July 2020, and plan review was completed the same month. Construction began in October 2020. The final inspection passed in January 2026, marking the completion of the physical construction phase. The TDLR status is now Project Closed, indicating that all regulatory requirements for the accessibility review process have been satisfied.

Project Closed

Project has been completed and closed

Follow this project

Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.

Or watch all projects in 75098 (Wylie)

One email per change. Unsubscribe in one click. Privacy.

NTMWD Muddy Creek Administration Building Improvement and Expansion is a Additions to Existing Building project located at 5400 Pleasant Valley Road, Wylie, TX 75098 in Wylie, Texas. The project has an estimated value of $974K covering 3,968 sq ft. North Texas Municipal Water District is the property owner and Huitt-Zollars, Inc. is the design firm of record. The project was registered with TDLR on July 30, 2020.

Frequently Asked Questions

What was the total cost of the Muddy Creek expansion?

The estimated cost for the 3,968-square-foot expansion was $973,558, averaging $245 per square foot.

Who designed the Muddy Creek Operations Building addition?

Huitt-Zollars, Inc. was the design firm of record for this project in Wylie.

When was the final inspection passed for this project?

The final inspection passed in January 2026, following a construction start in October 2020.

What features were added to the existing building?

The expansion included new locker rooms, a break room, utilities, and a breezeway connecting the old and new structures.

Is the North Texas Municipal Water District facility open?

The TDLR record confirms the construction is complete and the file is closed, but it does not specify public operating hours.

What is NTMWD Muddy Creek Administration Building Improvement and Expansion?

NTMWD Muddy Creek Administration Building Improvement and Expansion is a additions to existing building project at 5400 Pleasant Valley Road in Wylie, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Improvement to existing operations facility with expansion for locker rooms, break room and utilities. Connection between existing facility and new expansion via breezeway.

Is NTMWD Muddy Creek Administration Building Improvement and Expansion open in Wylie?

Construction on NTMWD Muddy Creek Administration Building Improvement and Expansion is complete — TDLR records show the project passed its required accessibility inspection in Sep 2026. The building is finished and very likely open.

Where is NTMWD Muddy Creek Administration Building Improvement and Expansion located?

NTMWD Muddy Creek Administration Building Improvement and Expansion is located at 5400 Pleasant Valley Road, Wylie, TX, 75098, in Taylor County.

Who is the owner or developer of NTMWD Muddy Creek Administration Building Improvement and Expansion?

North Texas Municipal Water District is the property owner/developer of record for NTMWD Muddy Creek Administration Building Improvement and Expansion, per its TDLR project registration.

Who is the architect or design firm for NTMWD Muddy Creek Administration Building Improvement and Expansion?

Huitt-Zollars, Inc. is the design firm of record for NTMWD Muddy Creek Administration Building Improvement and Expansion, according to its TDLR filing.

How much does NTMWD Muddy Creek Administration Building Improvement and Expansion cost and how big is it?

NTMWD Muddy Creek Administration Building Improvement and Expansion has an estimated construction value of $974K and approximately 3,968 square feet (about $245/sqft), based on its TDLR filing.

Scope of Work

Improvement to existing operations facility with expansion for locker rooms, break room and utilities. Connection between existing facility and new expansion via breezeway.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

Location & views

5400 Pleasant Valley Road, Wylie, TX, 75098

Explore the supplied address

A precise map point has not been loaded. Choose to look up the address, or open it in Google Maps using the link below.

Location by street address

Watch all construction in 75098 (Wylie)

A short email when anything new is filed in this ZIP. One ZIP free, weekly.

Unsubscribe in one click. Privacy.