This project involves public funds, public land, or is a Federally funded roadway project.
Lee Penn Park Pool and Bathhouse in Waxahachie, TX
404 N Getzendaner St, Waxahachie, TX, 75165
Lee Penn Park Pool and Bathhouse is a new construction project at 404 N Getzendaner St, Waxahachie, in Ellis County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Scheduled to finish Jul 2022 per its TDLR filing; no final inspection recorded yet. The project has an estimated value of $750K across about 2,739 sq ft.
- Estimated project value
- $750K
About this figure
Estimated construction cost supplied in the TDLR filing. This is not a current property appraisal or a final construction invoice.
- Reported floor area
- 2,739 ft²
About this figure
Square footage reported for this scope of work. It may cover only part of a larger property.
- Estimated cost / ft²
- $274/sqft
About this figure
Calculated from this filing’s estimated cost divided by its reported square footage. Available only when both figures are supplied; it is not a market benchmark.
- Scheduled duration
- 11 months
About this figure
The interval between the filed start and completion dates. These dates describe the proposed schedule and do not measure actual construction progress.
The project record
Project timeline
Explore filed milestones and scheduled dates. Open a milestone for its source.
4 timeline dates shown.
Project registered · TDLR filing
Registration of the project with the Texas Department of Licensing and Regulation.
Source: TDLR filing
View source recordReview complete · TDLR filing
The filing records completion of the accessibility review.
Same day as the preceding date shown.
Source: TDLR filing
View source recordScheduled construction start · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
89 days after the preceding date shown.
Source: TDLR filing
View source recordScheduled completion · Scheduled date
A date supplied in the filing; this does not confirm that work started or finished.
334 days after the preceding date shown.
Source: TDLR filing
View source record
📰About Lee Penn Park Pool and Bathhouse
The Lee Penn Park Pool and Bathhouse project in Waxahachie involves the new construction of a bathhouse and pool at 404 N Getzendaner St. The City of Waxahachie is the owner of record for this 2,739 sq ft facility, which carries an estimated cost of $750,000. This public works project is registered with TDLR and falls under the jurisdiction of Ellis County, utilizing public funds for its development.
Fitzpatrick Architects serves as the design firm of record. The project was registered with TDLR in May 2021, with plan review completed in the same month. Construction was scheduled to begin in August 2021, with a target completion date of July 2022. However, the Texas Department of Licensing and Regulation has not yet recorded a final inspection, so the current state of the site is not confirmed in the public record.
Project Scale and Cost Context
At $274 per square foot, the estimated cost exceeds the Ellis County median of $148 per square foot for similar new construction filings. The total estimated cost of $750,000 is below the county median of $900,000. The scheduled build window of 334 days is longer than the county median of 244 days. These figures are derived from 923 TDLR-registered new construction filings in Ellis County.
The City of Waxahachie has six other TDLR-registered projects totaling $21,003,870. These include the Fire Rescue Station No. 1 and Central Offices. Fitzpatrick Architects has designed six other projects totaling $9,340,000, including the Plaza Tower in Tyler and facilities in Rusk. The project is located in ZIP code 75165, which has a population of about 51,203 and a median household income of $84,780 according to U.S. Census estimates.
Local coverage from waxahachietx.com reported that the renovation project at the Lee Penn Park pool and bathhouse was expected to be complete in time for the swimming season. This third-party observation contrasts with the TDLR record, which still lacks a final inspection entry. The Ellis County unemployment rate was 4.5 percent in July 2026, higher than a year earlier.
Review Complete
Design review complete, construction may proceed
Follow this project
Get an email when the status changes — permits pulled, construction started, work finished. Free, and nothing else.
Or watch all projects in 75165 (Waxahachie)
One email per change. Unsubscribe in one click. Privacy.
Lee Penn Park Pool and Bathhouse is a New Construction project located at 404 N Getzendaner St, Waxahachie, TX 75165 in Waxahachie, Texas. The project has an estimated value of $750K covering 2,739 sq ft. City of Waxahachie is the property owner and Fitzpatrick Architects is the design firm of record. The project was registered with TDLR on May 4, 2021.
Frequently Asked Questions
Is the Lee Penn Park Pool and Bathhouse open to the public?
The TDLR record has not yet recorded a final inspection, so the facility's operational status is not confirmed in the public construction record. Local media reported it was expected to be ready for the swimming season.
Who is building the new bathhouse and pool?
The City of Waxahachie is the owner of record. Fitzpatrick Architects is the design firm of record. The project involves the new construction of a bathhouse and pool at 404 N Getzendaner St.
What is the estimated cost of the project?
The estimated cost is $750,000. This is below the Ellis County median of $900,000 for new construction, though the cost per square foot is above the county median.
When was construction scheduled to finish?
Construction was scheduled to finish in July 2022. However, TDLR has not yet recorded a final inspection, so the completion status is not confirmed in the public record.
Who designed the facility?
Fitzpatrick Architects is the design firm of record. They have designed six other TDLR-registered projects totaling $9,340,000, including facilities in Tyler and Rusk.
What is Lee Penn Park Pool and Bathhouse?
Lee Penn Park Pool and Bathhouse is a new construction project at 404 N Getzendaner St in Waxahachie, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction of bathhouse and pool
Is Lee Penn Park Pool and Bathhouse open in Waxahachie?
Lee Penn Park Pool and Bathhouse was scheduled to finish construction in Jul 2022 according to its TDLR registration, but TDLR has not recorded a final accessibility inspection, so its opening status is not confirmed in the public record.
Where is Lee Penn Park Pool and Bathhouse located?
Lee Penn Park Pool and Bathhouse is located at 404 N Getzendaner St, Waxahachie, TX, 75165, in Ellis County.
Who is the owner or developer of Lee Penn Park Pool and Bathhouse?
City of Waxahachie is the property owner/developer of record for Lee Penn Park Pool and Bathhouse, per its TDLR project registration.
Who is the architect or design firm for Lee Penn Park Pool and Bathhouse?
Fitzpatrick Architects is the design firm of record for Lee Penn Park Pool and Bathhouse, according to its TDLR filing.
How much does Lee Penn Park Pool and Bathhouse cost and how big is it?
Lee Penn Park Pool and Bathhouse has an estimated construction value of $750K and approximately 2,739 square feet (about $274/sqft), based on its TDLR filing.
Scope of Work
Construction of bathhouse and pool
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
Location & views
404 N Getzendaner St, Waxahachie, TX, 75165
Related Projects
Same Owner
$44.9M totalWatch all construction in 75165 (Waxahachie)
A short email when anything new is filed in this ZIP. One ZIP free, weekly.
Unsubscribe in one click. Privacy.
Keep exploring
What else is changing in Waxahachie?
See the surrounding filings, compare the reported schedules, and follow the places that matter to you.