2021 Street Improvements Project

Wildewood Drive from FM 2410, Harker Heights, TX 76548, Harker Heights, TX, 76548
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2022006789
$112K
Project Value
11,700
Square Feet
$10/sqft
Cost/SqFt
5 months
Duration
Registered:Dec 7, 2021
Start:Oct 31, 2021
Target:Mar 31, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of a 5-foot wide sidewalk, including curb ramps, from the intersection of Wildewood and FM2410 (Knight's Way), north to halfway between the intersections of Wildewood and Ramblewood and Wildewood and Pioneer Trail. Total distance is appr

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 7, 2021
Construction Start
October 31, 2021
Expected Completion
March 31, 2022

Quick Actions

TDLR ID: TABS2022006789

Registered Accessibility Specialist

๐Ÿ“‹
STEVEN E,RINEHART
RAS #1141
PO BOX 2436, HARKER HEIGHTS, TX 76548